8.180 This section covers Network Rail‟s plans for renewals in CP5. Its proposed volumes of asset renewal during the period are set out in Tables 8.11 to 8.13. These tables set out some of the key volumes planned by Network Rail; they do not capture all volumes proposed. We have worked with Network Rail to develop appropriate

renewal volume indicators for CP5 and these will be included in its delivery plan. The company‟s planned renewals expenditure and efficiencies are set out in Tables 8.14 to 8.16.

Volumes

8.181 Network Rail has forecast track renewals volumes for CP5 based on the new ways of working defined by its track policy. This has made comparison of volumes to CP4 difficult. Conversion of the volumes to kilometres of rail, sleeper and ballast renewal, and number of S&C units show that the company plans to deliver fewer kilometres of

rail and sleepers, more kilometres of ballast and significantly more S&C units. These changes are mainly driven by the new policy, but also include accelerated renewals. 8.182 Signalling volumes, as measured in Signalling Equivalent Units (SEUs), are forecast

to be much higher in CP5 than in CP4. Total SEU renewals almost double, from approximately 5,800 in CP4 to approximately 11,000 in CP5. The increase is largely driven by renewals associated with delivery of NOS. The SEU volume for CP5 shows a marked increase in ETCS delivered units, in line with the national strategy. The number of level crossings renewals to be delivered also increases from 123 in CP4 to 499 in CP5, again largely driven by NOS and requirements for obstacle detection. 8.183 Network Rail forecasts that its new civils asset policy requires a step-change in civil

asset renewals volumes, with increases relative to CP4 in almost all work types. Volumes of underbridge works are forecast to increase by 101%, volumes of

overbridge works by 7%, volumes of tunnels works by 58% and volumes of coastal and estuarial defence works by 141%.

8.184 Volumes of renewals relating to buildings assets have not been captured during CP4 but have been forecast for CP5 for franchised and managed station assets.

8.185 Plans for electrification and fixed plant show increased volumes of conductor rail and low voltage DC (LVDC) distribution cables compared to CP4. AC distribution volumes are significantly lower than in CP4 as are all DC distribution volumes with the

exception of LVDC distribution cables. A high volume of signalling power cable renewals is planned to address a recently identified backlog of work. The plans include new volume measures for CP5, including volumes of overhead line mid-life refurbishments and of signalling power cable renewals.

Table 8.11: Network Rail's planned renewal volumes (subset of main categories), Great Britain

Volumes Units CP5 CP5

2014-15 2015-16 2016-17 2017-18 2018-19 Total

Track

Conventional plain line, heavy refurb (concrete, MO)

km 108 162 218 227 211 926

Conventional plain line, rail renewal

km 267 239 272 267 250 1,294

Conventional plain line, single rail

km 36 33 37 39 36 180

Conventional plain line, steel relay

km 11 11 16 22 10 70

Conventional plain line, complete Trax

Volumes Units CP5 CP5 2014-15 2015-16 2016-17 2017-18 2018-19 Total

High output, heavy refurb (concrete, HO)

km 0 67 56 0 48 171

High output, rail sleeper relay

km 126 83 191 187 171 757

Plain line refurb, heavy (other)

km 41 38 36 39 35 189

Plain line refurb, medium (concrete)

km 191 205 210 214 234 1,054

Plain line refurb, medium (other)

km 169 175 170 194 191 898

S&C, full renewal S&C 325 289 343 272 282 1,510 S&C, heavy refurb S&C 263 324 393 427 432 1,841 S&C, medium refurb S&C 428 431 435 410 424 2,130 Signalling

Conventional resignalling SEU 1,742 2,769 2,559 1,715 1,048 9,832

ETCS resignalling SEU 0 80 115 146 868 1,209

Level crossings no. 58 95 137 124 85 499

Civils Overbridges sq ms 10,012 10,012 10,012 10,012 10,012 50,062 Underbridges sq ms 156,530 153,468 154,031 153,463 156,846 774,337 Tunnels sq ms 24,627 24,627 24,627 24,627 24,627 123,136 Buildings (franchised stations)

Building - Roof Structure sq ms 20,493 4,934 2,660 2,879 2,549 33,515 Platform - Surface sq ms 69,868 62,404 85,518 56,410 29,137 303,337 Canopy - Roof Structure sq ms 21,195 18,093 20,729 18,305 16,058 94,380 Train Shed - Roof

Structure

sq ms 30,314 10,613 22,480 2,765 450 66,622 Footbridge - Surface sq ms 5,855 3,337 5,049 4,578 2,663 21,482 Electrical power and fixed

plant

Overhead line mid-life refurb

wire runs

59 70 70 65 52 316

Overhead line structure renewal no. 116 158 186 63 99 621 DC distribution HV switchgear renewals no. 17 36 3 9 3 68 DC distribution HV cable km 47 25 28 21 21 142

Volumes Units CP5 CP5 2014-15 2015-16 2016-17 2017-18 2018-19 Total

LV DC switchgear renewal no. 82 78 70 69 34 332

Conductor rail renewal km 40 32 40 23 15 149

Signalling power distribution

km 299 267 248 189 152 1,155

Telecoms

SISS CIS no. 251 565 735 531 483 2,565

SISS PA no. 2,662 2,265 2,242 2,113 1,714 10,996

SISS CCTV no. 1,007 1,466 1,377 394 351 4,596

Table 8.12: Network Rail's planned renewal volumes (subset of main categories), England & Wales

Volumes Units CP5 CP5

2014-15 2015-16 2016-17 2017-18 2018-19 Total

Track

Conventional plain line, heavy refurb (concrete, MO)

km 95 149 182 191 175 793

Conventional plain line, rail renewal

km 241 213 246 241 224 1,164

Conventional plain line, single rail

km 24 21 24 27 24 120

Conventional plain line, steel relay

km 3 3 8 14 2 30

Conventional plain line, complete Trax

km 176 160 154 170 171 831

High output, ABC km 235 195 171 137 178 915

High output, heavy refurb (concrete, HO)

km 0 67 56 0 48 171

High output, rail sleeper relay

km 126 83 169 165 149 692

Plain line refurb, heavy (other)

km 41 38 36 39 35 189

Plain line refurb, medium (concrete)

km 112 127 132 136 156 662

Plain line refurb, medium (other)

km 127 133 128 152 149 689

S&C, full renewal S&C 298 262 316 245 255 1,376 S&C, heavy refurb S&C 238 299 368 402 407 1,714 S&C, medium refurb S&C 385 388 392 367 381 1,913

Volumes Units CP5 CP5 2014-15 2015-16 2016-17 2017-18 2018-19 Total

Signalling

Conventional resignalling SEU 1,725 2,514 1,867 1,594 966 8,666

ETCS resignalling SEU 0 80 115 146 868 1,209

Level crossings no. 53 95 126 123 81 478

Civils Overbridges sq ms 8,941 8,941 8,941 8,941 8,941 44,706 Underbridges sq ms 133,845 132,073 132,391 130,723 133,470 662,504 Tunnels sq ms 20,400 20,400 20,400 20,400 20,400 102,000 Buildings (franchised stations)

Building - Roof Structure sq ms 20,173 4,669 2,638 2,879 2,549 32,908 Platform - Surface sq ms 69,868 62,404 85,408 56,410 29,137 303,227 Canopy - Roof Structure sq ms 21,195 18,093 20,729 18,281 16,058 94,356 Train Shed - Roof

Structure

sq ms 30,314 10,613 22,400 2,395 0 65,722 Footbridge - Surface sq ms 5,855 3,337 5,049 4,578 2,663 21,482 Electrical power and fixed

plant

Overhead line mid-life refurb

wire runs

56 67 67 62 49 301

Overhead line structure renewal no. 113 155 183 60 96 606 DC distribution HV switchgear renewals no. 17 36 3 9 3 68 DC distribution HV cable km 47 25 28 21 21 142

LV DC switchgear renewal no. 82 78 70 69 34 332

Conductor rail renewal km 40 32 40 23 15 149

Signalling power distribution

km 272 240 220 149 121 1,001

Telecoms

SISS CIS no. 228 565 727 502 449 2,470

SISS PA no. 2,662 1,471 2,242 2,113 1,714 10,202

Table 8.13: Network Rail's planned renewal volumes (subset of main categories), Scotland

Volumes Units CP5 CP5

2014-15 2015-16 2016-17 2017-18 2018-19 Total

Track

Conventional plain line, heavy refurb (concrete, MO)

km 13 13 36 36 36 134

Conventional plain line, rail renewal

km 26 26 26 26 26 130

Conventional plain line, single rail

km 12 12 12 12 12 61

Conventional plain line, steel relay

km 8 8 8 8 8 40

Conventional plain line, complete Trax

km 34 34 34 34 34 171

High output, ABC km 0 0 0 0 0 0

High output, heavy refurb (concrete, HO)

km 0 0 0 0 0 0

High output, rail sleeper relay

km 0 0 22 22 22 65

Plain line refurb, heavy (other)

km 0 0 0 0 0 0

Plain line refurb, medium (concrete)

km 78 78 78 78 78 392

Plain line refurb, medium (other)

km 42 42 42 42 42 209

S&C, full renewal S&C 27 27 27 27 27 134

S&C, heavy refurb S&C 25 25 25 25 25 127

S&C, medium refurb S&C 43 43 43 43 43 217

Signalling

Conventional resignalling SEU 17 255 692 121 82 1,167

ETCS resignalling SEU 0 0 0 0 0 0

Level crossings no. 5 0 11 1 4 21

Civils Overbridges sq ms 1,071 1,071 1,071 1,071 1,071 5,356 Underbridges sq ms 22,685 21,395 21,639 22,740 23,375 111,834 Tunnels sq ms 4,227 4,227 4,227 4,227 4,227 21,137 Buildings (franchised stations)

Volumes Units CP5 CP5 2014-15 2015-16 2016-17 2017-18 2018-19 Total

Platform - Surface sq ms 0 0 110 0 0 110

Canopy - Roof Structure sq ms 0 0 0 24 0 24

Train Shed - Roof Structure

sq ms 0 0 80 370 450 900

Footbridge - Surface sq ms 0 0 0 0 0 0

Electrical power and fixed plant

Overhead line mid-life refurb

wire runs

3 3 3 3 3 15

Overhead line structure renewal no. 3 3 3 3 3 15 DC distribution HV switchgear renewals no. 0 0 0 0 0 0 DC distribution HV cable km 0 0 0 0 0 0

LV DC switchgear renewal no. 0 0 0 0 0 0

Conductor rail renewal km 0 0 0 0 0 0

Signalling power distribution

km 27 27 28 40 31 154

Telecoms

SISS CIS no. 23 0 9 29 34 94

SISS PA no. 0 794 0 0 0 794

SISS CCTV no. 0 0 0 0 0 0

Efficiency

8.186 Network Rail has proposed CP5 exit renewals efficiencies of 15.8% for the network, 15.5% for Scotland and 15.9% for England & Wales170.

8.187 The company has set out plans for its renewals efficiencies in a series of business cases. Key areas for delivering efficiencies are:

(a) development of policies which Network Rail considers to be better optimised for minimum whole life cost;

(b) asset information efficiencies to be delivered by ORBIS; (c) better scheduling of work;

170 In Network Rail‟s SBP it presented renewals efficiency for „core‟ asset renewals only, which it

defined as track, signalling, civils, buildings, telecoms, and electrification and plant. It presented figures excluding the efficiencies which are built into its CP5 asset policies. Figures presented here are for all renewals expenditure and include the efficiencies which are built into its CP5 policies.

(d) more effective contractual relationships; (e) standardisation of processes; and (f) multi-skilling of staff.

8.188 Efficiencies are discussed by main asset category later in the chapter.

Expenditure

8.189 Network Rail forecasts renewals expenditure of £13.6bn across the network, £1.48bn in Scotland and £12.1bn in England & Wales. This level of expenditure is considerably higher than in CP4 despite efficiencies achieved in CP4 and forecast to the end of CP5, and despite an accounting change moving costs from renewals to maintenance. Network Rail‟s key proposals which drive this increase in expenditure are:

(a) the rationalisation and centralisation of signalling control through implementation of NOS;

(b) a large increase in proposed expenditure on civil structures and earthworks renewals resulting from the application of the updated policy and a better

understanding of asset condition, degradation and risk, the net effect of which is forecast to deliver a step-change improvement in the level of civil assets risk on the network;

(c) renewals brought forward from future control periods to deliver work more

effectively, for example as the result of enhancement schemes, or to make use of access before it is limited by traffic growth;

(d) proposed expenditure on improving asset information systems and management, ORBIS; and

(e) a proposal for additional investment schemes where Network Rail believes there is a business case. For example it has proposed additional investment in

improved information technology, Research & Development (R&D), safer and faster isolations and a new system to provide alerts to track workers.

Table 8.14: Network Rail's plans, renewals, Great Britain £m (2012-13 prices) CP4 CP5 CP4 CP5 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Total Total Pre-efficient expenditure - 2,989 3,149 3,196 3,119 3,060 - 15,513 Efficiency - 8.3% 2.8% 2.8% 1.5% 1.4% - 15.8% Post-efficient expenditure 2,784 2,741 2,808 2,771 2,663 2,576 12,833 13,559

Table 8.15: Network Rail's plans, renewals, England & Wales £m (2012-13 prices) CP4 CP5 CP4 CP5 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Total Total Pre-efficient expenditure - 2,672 2,756 2,839 2,795 2,743 - 13,805 Efficiency - 8.1% 2.9% 2.6% 1.6% 1.5% - 15.9% Post-efficient expenditure 2,510 2,455 2,458 2,465 2,388 2,308 11,446 12,074

Table 8.16: Network Rail's plans, renewals, Scotland £m (2012-13 prices) CP4 CP5 CP4 CP5 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Total Total Pre-efficient expenditure - 316 393 357 325 316 - 1,708 Efficiency - 9.6% 1.4% 4.1% 0.8% 0.3% - 15.5% Post-efficient expenditure 273 286 350 305 275 267 1,387 1,484

Outputs

8.190 Network Rail has forecast the asset condition and performance metrics which its policies will deliver as described in chapter 3. For both condition and performance its approach is, in the main, to keep asset specific metrics constant at the level forecast for the end of CP4. However, for civil structures, earthworks and off-track it is planning an improvement in overall condition. For track, number of failures per year causing delays of greater than 10 minutes is forecast to increase marginally. For electrification and plant the same metric is forecast to increase by approximately 10%. For

structures, the number of open risk items with a risk score of greater than 20 is expected to reduce significantly by the end of CP5.