• No se han encontrado resultados

Electromechanical oscillation damping in one hydraulic central

N/A
N/A
Protected

Academic year: 2017

Share "Electromechanical oscillation damping in one hydraulic central"

Copied!
1
0
0

Texto completo

(1)

Electromechanical Oscillation Damping in one Hydraulic Central

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

J.L.

Agiiero

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

Member IEEE

IITREE-LAT. Facultad de Ingenieria.

Universidad Nacional de La Plata

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

( 1900) 48

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

y 1 16. La Plata. Argentina

Abstract: Studies, simulations, and tests carried out to damp

electromechanical oscillations are

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

described. The solution was to

install Power System Stabilizer

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

( P S S ) in 4 generator of 118

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

M W

each one, located in one hydraulic plant. This plant is connected to “Sistema Elktrico Patag6nico Interconectado (SEPI)” trough a double 330 kV transmission line, with its far end connected to one

aluminum plant with two 160 MW series of 200 electrolytic cells

each one. Studies began with whole

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

system data base validation,

included the aluminum plant dynamic load model. Modal analysis and temporal simulation of event that excite dominant electromechanical oscillation mode were done. PSS tuning

parameters were found, and the reciprocal influences between PSS

and turbine governor were minimized . PSS commissioning test were

zyxwvutsrqponmlkjihgfedcbaZYXWVUTSRQPONMLKJIHGFEDCBA

carried out, and the results are compared with previous studies, showing a good agreement.

Keywords: Load modeling. Power System Stabilizer. Excitation Control. Turbine Governor. Power System Dynamic Stability.

I. INTRODUCTION

The SEPI is

an

electrical system relatively small, their peak

load is of approximately 600 MW, has a hydraulic power plant with four units of 118 MW each one, that connects through one double line of 330 kV and 550 Ian, with a

aluminum plant. The rest of the system has 1300 km in 1328

kV lines, with distributed load and generation, in radial configuration, being an important part of this demand constituted by motors in petroleum deposits.

The aluminum plant is constituted by two electrolytic series of 200 cells each one, and has gas turbine electric generation.

In Fig 1 is indicated

a

simplified

scheme of SEPI, showing the present situation of the aluminum plant and its future

enlargement. The values of demand of the electrolytic series, and the installed generator powers in the aluminum plant and tbe hydraulic power plant have been indicated.

There was a restriction to the power transmission on the double line of 330 kV, because the operation experience and previous studies indicate the presence of

an

electromechanical oscillation with not acceptable damping.

Abstract ID

Number:

99

SM

100

0-7803-5569-5/99/$10.00 Q 1999 IEEE

M. Beroqui

Prof. Ppal. CIC

IITREE-LAT. Facultad de Ingenieria.

Universidad Nacional de La Plata (1900) 48 y 116. La Plata. Argentina

3 3 0 / 1 3 2 k V L I N E S

3 3 O k V

AUTO TRANSFORMER

i HYDROELECTRIC : j CENTRAL j

.______ ~ _.__ _.__ ____.____

__

132Kv

REST Of S E P I

12OMW 120MW

j BSMW 16OMW 85MW 160MW

ALUMINUM PLANT FUTURE ENLARGEMEN]

Fig. 1: SEPI simplify scheme.

By such a reason, the power hydraulic plant agent commissioned the necessary studies. These studies began with the conformation of a Database for dynamic studies, validated with data contributed by manufacturer and tests made previously.

A particular interest was put to find

a

load model that represents suitably the aluminum plant, specially in the frequency range of the electromechanical oscillations.

Also, the model of the excitation control system of the

hydraulic machines was verified by tests.

Then different study scenarios were considered those include present situations and future enlargements of the

SEPI, as

much in lines, as in instaUation of new generators and new demands.

As

the power hydraulic power plant is located in a SEPI far end and is the greatest generator in this

system, all the possible participation cases in the system dispatch were analyzed, with the lowest and highest possible hydraulic head.

The

PSS

effectiveness was analyzed, with PSS working with electrical power or accelerating power signals. The reduction of the

PSS

negative impact over the turbine governor was evaluated, selecting the most appropriate adjustment. Finally, tests were made in the PSS commission, to vetify their correct performance.

II.

DATABASE

All the necessary models for the studies were determined

previously, from manufacturer information, or tests made in the past, or specific tests made to such aim.

In those cases when there were not test information, the recommended model and typical adjustments were taken, between many others: from [I] for the excitation controls; from [21 for turbine governors, and from [3] for the machine

[image:1.616.321.556.152.337.2]

Figure

Fig. 1: SEPI simplify scheme.

Referencias

Documento similar

Que o Espírito Santo, promessa de Cristo que não nos deixaria órfãos infunda em nós o dom do entendimento para compreendermos as verdades da fé e os ensinamentos de Jesus.A

The Dome of the Rock does attest the existence, at the end of the seventh century, of materials immediately recognisable as Koranic in a text that not infrequently

On one hand, we analyze what kind of contexts the usability evaluation and the perspective of the user's experience are being studied. On the other hand, our aim was to know

There was no increment of unmeasured anions in the control.. animal studies where the presence of metabolic acidosis de- layed the progression of renal failure through prevention

Consequently, the aim of this research was, on the one hand to analyze the direct association of impulsivity and sensation seeking scales (thrill and adventure seeking,

In this context, to study the transmission of the financial crisis on the macroeconomic variables (output, export, and import), we apply a non-stationary test in the presence of

The problem analyzed in the previous sections was used as an introductory situation in one of the topics of mathematics for teachers in a training course for in-training

Parameters of linear regression of turbulent energy fluxes (i.e. the sum of latent and sensible heat flux against available energy).. Scatter diagrams and regression lines