WMI CRAES LTD., one of the leading manufacturers of Cranes in India, has been pioneers in the manufacture of Material Handling Equipment in the Country. Today WMI`s name is synonymous with heavy lifting. WMI’s equipment can be found in all parts of the Country, helping others get their jobs done faster and easier. An array of WMI cranes have been developed, each crane a creative solution to special handling problem. These cranes are extensively used for handling materials in machine shops, structural shops, chemical plants, fertilizer plants, cement factories, paper plants, stock yards, Dams, and construction sites. All WMI cranes are engineered and built to meet the requirements of all the users. Thus tailor-made for the job, these units handle the loads with utmost ease of maintenance efficiency and economy.

4.2.1.5.1 E. O. T. CRAES

These cranes move on the gantry rail fixed to gantry girder. In this crane 3 common motions are incorporated - hoist, cross travel and long travel. In addition to these common motions some time depending on duty, Aux. Hoist is incorporated. Hoist and C. T. Machineries are fitted on common frame called crab which moves on crane girders.

In refinery, there are two EOT cranes. These cranes play major role in the overall functioning of the refinery whether it be cellhouse, CSM, APM, or ASWM. Even in regular activities other than processes the crane plays a significant role in the refinery. Any delay caused by the crane causes a major delay in all the machineries and the processes.

Some of the major delays occurred in CRANE-1 in NOV-09 TO MARCH-10 are given below:

DELAY AREAS TOTAL

LT 1292

MH 1105

DSL 730

DRIP TRAY 311

HOOK 145

COMPRESSOR 113

REMOTE PAEL 60

CT 40

AH 0

LIK 0

SPREADER BEAM 0

Table 4.7

40 IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

4.2.1.5.2 PARETO AALYSIS:

In crane-1 the area which has frequent problem delay is the long travel. Some of the common delays in long travel are as follows:

1. LT got tripped.

2. LT PLC problem.

3. LT slow movement.

4. LT brake problem.

5. LT 2 drives taking delay.

The second area which causes the major delay in crane problems are as follows:

1. MH got tripped.

2. MH not getting down (Due to drip tray 3. MH brake not good.

Third most delay prone area is the DSL. Some common problems occurring in DSL are:

1. Remote signal cut off problem.

2. Whole crane got tripped.

0

IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

4.2.1.5.2 PARETO AALYSIS:

Fig 4.9

1 the area which has frequent problem delay is the long travel. Some of the common delays in long travel are as follows:

LT 2 drives taking delay.

The second area which causes the major delay in crane-1 is main hoist. Some of the common

MH not getting down (Due to drip tray L/S activated).

Third most delay prone area is the DSL. Some common problems occurring in DSL are:

Remote signal cut off problem.

Whole crane got tripped.

DRIP TRAY HOOK COMPRESSOR REMOTE PANEL CT AH LINK SPREADER BEAM

IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

1 the area which has frequent problem delay is the long travel. Some of the common

1 is main hoist. Some of the common

Third most delay prone area is the DSL. Some common problems occurring in DSL are:

SPREADER BEAM

Series1 Series2

41 IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

The delay problems are also divided among the departments as mechanical, electrical, process, instrumentation and cranes. The consolidated delay distribution of the departments from NOV’09-MARCH’10 is provided below:

DELAY AREAS TOTAL

MECHAICAL 1368

ELECTRICAL 3196

ISTRUMETATIO 12

PROCESS 178

CRAES 0

Table 4.8 4.2.1.5.3 PARETO AALYSIS:

Fig 4.10

Electrical problems are the major delay causes in the crane-1. Some of the common mechanical problems faced by the crane-1 are as follows:

1. MH- M.H got tripped.

2. DSL- Remote signal cut off problem.

3. Drip tray- Drip tray got tripped.

4. CT- CT got tripped

Secondly, mechanical problems cause delay in large number for crane-1. Some of these problems are:

1. LT- abnormal sound in rails.

2. Link- Cathode hook link got broken.

3. Hook- Anode hook struck up problem.

0 20 40 60 80 100

ELECTRICAL MECHANICAL PROCESS INSTRUMENTATI ON CRANES

Series1 Series2

42 IMPROVIG THE OPERATIOAL EFFICIECY AD

As we see the Pareto chart, it is clear that in crane

main hoist. Some of the problems frequently occurring in the main hoist are as follows:

1. MH brake not good.

IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

the Pareto chart, it is clear that in crane -2 the major problem causing area is the main hoist. Some of the problems frequently occurring in the main hoist are as follows:

DSL CT LT HOOK LINK SPREADER BEAM DRIP TRAY REMOTE PANEL

IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

2 the major problem causing area is the main hoist. Some of the problems frequently occurring in the main hoist are as follows:

REMOTE PANEL

Series1 Series2

43 IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

The delay problems are also divided among the departments as mechanical, electrical, process, instrumentation and cranes. The consolidated delay distribution of the departments from NOV’09-MARCH’10 is provided below:

DELAY AREAS TOTAL

ELECTRICAL 1268

PROCESS 94

MECHAICAL 77

ISTRUMETATIO 0

CRAES 0

Table 4.10 4.2.1.5.5 PARETO AALYSIS:

Fig 4.12

Electrical problems are the major delay causes in the crane-1. Some of the common mechanical problems faced by the crane-1 are as follows:

1. MH- M.H got tripped.

2. DSL- Remote signal cut off problem.

3. Drip tray- Drip tray got tripped.

4. CT- CT got tripped

In crane-2 the second delay causing problem is process delays. Some of the common process delays is Hook- Cathode hook link got broken/bend.

0 10 20 30 40 50 60 70 80 90 100

ELECTRICAL PROCESS MECHANICAL INSTRUMENTATION CRANES

Series1 Series2

44 IMPROVIG THE OPERATIOAL EFFICIECY AD PROFITABILITY OF EXPORT ORIETED UIT

4.2.1.6 OPERATOR SKILLS AD EXPERIECE: operators handling the various