Trench excavation shall be deemed to include preparation of surfaces, excavation for bedding, multiple handling, disposal of surplus excavated material (including unsuitable material), upholding sides of excavation, allowance for working space, backfilling, removal of dead services, and reinstatement of original surface unless covered by separate items.
100 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 100 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 100 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 100 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 100 mm DN pipe, depth 2.5 – 3.0 m. m
150 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 150 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 150 mm DN pipe, depth 1.5 – 2 m. m O113 In earth for 150 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 150 mm DN pipe, depth 2.5 – 3.0 m. m
200 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 200 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 200 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 200 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 200 mm DN pipe, depth 2.5 – 3.0 m. m
Page Total carried to Summary of Class O
\\vboxsrv\conversion_tmp\scratch_6\167229266.xls.ms_office
Class O: Pipework Page BQO111 of BQO173
300 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 300 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 300 mm DN pipe, depth 1.5 – 2 m. m O113 In earth for 300 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 300 mm DN pipe, depth 2.5 – 3.0 m. m
400 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 400 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 400 mm DN pipe, depth 1.5 – 2 m. m O113 In earth for 400 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 400 mm DN pipe, depth 2.5 – 3.0 m. m
500 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 500 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 500 mm DN pipe, depth 1.5 – 2 m. m O113 In earth for 500 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 500 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 500 mm DN pipe, depth 3.0 – 4.0 m. m
600 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 600 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 600 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 600 mm DN pipe, depth 2.0 – 2.5 m. m
CLASS O Pipework
Item No. Code No. Description Unit Qty. Rate Amount (RM)
O114 In earth for 600 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 600 mm DN pipe, depth 3.0 – 4.0 m. m
800 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 800 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 800 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 800 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 800 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 800 mm DN pipe, depth 3.0 – 4.0 m. m
1000 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 1000 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 1000 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 1000 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 1000 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 1000 mm DN pipe, depth 3.0 – 4.0 m. m
1200 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 1200 mm DN pipe, depth not exceeding 1.5 m
m
O112 In earth for 1200 mm DN pipe, depth 1.5 – 2 m m O113 In earth for 1200 mm DN pipe, depth 2.0 – 2.5 m m O114 In earth for 1200 mm DN pipe, depth 2.5 – 3.0 m m O115 In earth for 1200 mm DN pipe, depth 3.0 – 4.0 m m
Page Total carried to Summary of Class O
\\vboxsrv\conversion_tmp\scratch_6\167229266.xls.ms_office
Class O: Pipework Page BQO113 of BQO173
1400 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 1400 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 1400 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 1400 mm DN pipe, depth 2.0. – 2.5 m m O114 In earth for 1400 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 1400 mm DN pipe, depth 3.0 – 4.0 m. m
1600 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 1600 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 1600 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 1600 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 1600 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 1600 mm DN pipe, depth 3.0 – 4.0 m. m O116 In earth for 1600 mm DN pipe, depth 4.0 – 5.0 m. m
1800 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 1800 mm DN pipe, depth not exceeding 1.5 m.
m
O112 In earth for 1800 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 1800 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 1800 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 1800 mm DN pipe, depth 3.0 – 4.0 m. m O116 In earth for 1800 mm DN pipe, depth 4.0 – 5.0 m. m
CLASS O Pipework
Item No. Code No. Description Unit Qty. Rate Amount (RM)
2000 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O111 In earth for 2000 mm DN pipe, depth not exceeding 1.5 m.
2200 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
2400 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
2600 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O112 In earth for 2600 mm DN pipe, depth 1.5 – 2.0 m. m
Page Total carried to Summary of Class O
\\vboxsrv\conversion_tmp\scratch_6\167229266.xls.ms_office
Class O: Pipework Page BQO115 of BQO173
O113 In earth for 2600 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 2600 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 2600 mm DN pipe, depth 3.0 – 4.0 m. m O116 In earth for 2600 mm DN pipe, depth 4.0 – 5.0 m. m O117 In earth for 2600 mm DN pipe, depth 5.0 – 6.0 m. m
2800 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos. (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O112 In earth for 2800 mm DN pipe, depth 1.5 – 2.0 m. m O113 In earth for 2800 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 2800 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 2800 mm DN pipe, depth 3.0 – 4.0 m. m O116 In earth for 2800 mm DN pipe, depth 4.0 – 5.0 m. m O117 In earth for 2800 mm DN pipe, depth 5.0 – 6.0 m. m O118 In earth for 2800 mm DN pipe, depth exceeding 6.0 m. m
3000 mm DN pipe [Jalan Paip to Jalan Besi] as shown in Drawing Nos (…) to (…). Width of trench shall be as shown in Drawing No. (…) and Specification clause (…).
O113 In earth for 3000 mm DN pipe, depth 2.0 – 2.5 m. m O114 In earth for 3000 mm DN pipe, depth 2.5 – 3.0 m. m O115 In earth for 3000 mm DN pipe, depth 3.0 – 4.0 m. m O116 In earth for 3000 mm DN pipe, depth 4.0 – 5.0 m. m O117 In earth for 3000 mm DN pipe, depth 5.0 – 6.0 m. m O118 In earth for 3000 mm DN pipe, depth exceeding 6.0 m. m
Extras to Trench Excavation
O121 Rock. m3
O122 Natural hard material. m3
O123 Artificial hard material. m3
CLASS O Pipework
Item No. Code No. Description Unit Qty. Rate Amount (RM)
O124 Roads and pavement, rate to include road cutting and reinstatement.
m2
Excavation for Manholes and Chambers
O131.1 In earth for [manholes]. m3
O131.2 In earth for [valve chambers]. m3
O132.1 Roads and pavement for [manholes]. m2
O132.2 Roads and pavement for [valve chambers], rate to include road cutting and reinstatement.
m2
O133.1 Artificial hard material for [manholes]. m3 O133.2 Artificial hard material for [valve chambers]. m3 O134.1 Natural hard material for [manholes]. m3 O134.2 Natural hard material for [valve chambers]. m3
O135.1 In rock for [manholes]. m3
O135.2 In rock for [valve chambers]. m3
O200 BACKFILLING AND BEDDING MATERIALS