• No se han encontrado resultados

II – REVISION BIBLIOGRÁFICA

4 – CONSTRUCCIÓN DE MODELOS

The   benefits   of   the   BIM   technologies   span   the   entire   building/construction   lifecycle   starting   from   the   conceptual   design/feasibility   stage   to   handover   and   facility  maintenance  stage  or  even  up  to  the  decommissioning  or  demolition  of  the   building.   The   following   section   summarises   the   most   common   benefits   of   BIM   at   various  stages  of  the  construction  project  (Eastman  et  al.,  2011).  

4.4.1  Pre-­‐construction/Feasibility  Study  

At  this  stage  the  main  goal  is  to  understand  whether  the  desired  functions  from  a   building  or  a  structure  can  be  realised  within  the  available  budget  and  time.  BIM  

provides   a   platform   to   visually   appraise   the   spatial   requirements   and   rapidly   quantify  the  cost  and  time  aspects  of  the  project  by  linking  it  with  the  cost  data  in  a   parametric  way.  Specifically  the  following  benefits  are  realised:  

4.4.1.1  Improving  programme  certainty  through  spatial  analysis    

There   are   tools   available   to   automatically   check   models   against   spatial   requirements,   for   example   minimum   size   of   a   particular   type   of   room,   minimum   height  of  a  door  or  distance  between  the  wall  an  opening  (such  as  a  window).  By   automating  such  tasks,  the  quality  and  speed  of  design  improves  greatly.    

4.4.1.2  Rapidly  consider  and  explore  design  alternatives  

By   linking   the   parametric   BIM   model   to   cost   estimating   and   energy   analysis   systems,   it   is   possible   to   rapidly   evaluate   design   alternatives   to   analyse   the   performance  of  the  facility  from  cost,  time  and  performance  perspective.    

4.4.1.3  Receive  early  feedback  from  downstream  players  through  programme   simulation    

By   linking   a   high   level   project   plan   even   during   the   feasibility   study/concept   development  stage  and  developing  a  4D  model,  a  significant  amount  of  variability   can  be  reduced  by  carrying  out  a  constructability  review.  Having  a  4D  simulation   done  early  on  a  project  where  new  construction  or  refurbishment  is  taking  place   side-­‐by-­‐side   an   operational   building   can   also   help   identify   the   impact   of   construction  activities  on  building  operation.  

4.4.2  Design  and  Detail  

4.4.2.1  More  accurate  early  visualisation  of  design  

With   earlier   3D   (non   BIM)   technologies   where   geometric   models   were   created   with   non-­‐parametric   technologies,   significant   time   and   effort   was   required   to   generate   such   visualisations   and   on   many   occasions   they   were   not   accurate.   However,   with   the   advent   of   BIM   technologies,   it   is   now   possible   to   visualise   design   at   any   stage   with   accurately   reflects   what   has   been   designed.   This   is   significant  especially  at  early  stages  to  capture  the  design  intent  from  client  and  to   communicate  to  key  stakeholders.  

4.4.2.2  Automatic  propagation  of  design  changes  

Design   is   an   iterative   process   and   changes   are   made   constantly,   especially   when   design  from  various  sources  have  to  be  synchronised  (i.e.  structural,  architectural,   MEP).   With   BIM,   it   is   now   possible   to   control   and   link   the   object   properties   in   a   parametric  way,  and  hence  changes  made  to  one  object/element  ensures  that  all   connected  objects  change  their  properties  in  a  parametric  way.  

4.4.2.3  Generating  accurate  drawings  automatically    

Even  with  BIM,  it  is  necessary  to  generate  and  distribute  2D  drawings  at  certain   stages.  However,  drawing  generation  from  majority  of  BIM  system  is  an  automatic   process  and  drawings  always  correspond  to  the  current  model  ensuring  accuracy.   4.4.2.4  Better  collaboration  between  designers  

Synchronising   design   early   ensures   minimal   rework   and   improved   accuracy   and   quality   of   design.   With   BIM   it   is   possible   to   regularly   synchronise   design   and   perform  tasks  such  as  clash  detection.  This  ensures  that  design  is  error  free  and   any  constructability  or  performance  issues  are  identified  early.  

4.4.2.5  Linking  design  to  cost  estimates  

Many   design   decisions   are   linked   to   the   cost,   and   the   possibility   to   generate   automatic   cost   estimates   based   on   the   BIM   model   at   any   stage   during   design   enables   to   client   to   make   better   informed   decision.   It   can   also   help   during   the   bidding/tendering  stage  to  provide  an  accurate  bill  of  quantities  to  all  bidders.   4.4.2.6  Improving  Performance  of  the  Facility  

BIM   enables   carrying   out   sophisticated   simulation   such   as   acoustics,   energy   and   lighting   during   the   design   stage.   Again,   this   enables   the   client   to   make   informed   decisions   and   makes   sure   the   facility   performs   to   the   requirements.   With   government  imposing  stringent  guidelines  with  carbon  emissions,  it  helps  achieve   those  targets  and  improves  sustainability.    

4.4.3  Construction  

4.4.3.1  Performing  clash  detection    

With   BIM   it   is   possible   to   synchronise   design   models   from   all   disciplines   before   construction   begins   (and   also   during   construction   when   design   is   going   on   in  

parallel)   to   identify   any   hard   (physical)   or   soft   (tolerance)   clashes   between   elements.  This  ensures  that  these  issues  do  not  delay  the  construction  process  and   also  minimises  rework  if  the  clashes  are  found  after  construction  has  taken  place.     4.4.3.2  Using  4D/5D  for  production  planning  

When   a   project   plan   is   linked   to   a   BIM   model,   the   combined   model   is   called   4D.   When  cost  and  quantity  information  is  linked  to  such  a  model  the  model  is  called  a   5D   model.   Such   4D   and   5D   models   can   help   contractors   understand   how   a   construction   project   will   look   like   at   any   given   point   in   time.   This   functionality   greatly  depends  on  the  level  of  detail  the  model  is  based  upon  and  may  vary  if  the   temporary  structures  are  not  included  and  if  the  plan  is  only  at  a  high  level  (i.e.  a   master  plan).  

4.4.3.3  Prefabrication  with  BIM  

With  BIM  the  geometric  data  is  accurately  represented  and  this  enables  building   components   to   be   sent   directly   for   automated   fabrication   using   numerically   controlled   machines.   Steel   fabricated   components,   precast   concrete   elements,   fenestration   and   glass   fabrication   are   already   manufactured   on   construction   projects  using  this  method.  Offsite  construction  is  proven  to  improve  construction   quality  and  is  promoted  in  the  UK  by  the  Government.  

4.4.3.4  Integrating  supporting  systems  with  BIM  

Construction   is   a   complex   process   and   many   information   systems   related   to   supporting  activities  such  as  safety,  quality,  procurement  and  logistics  are  used  on   a  typical  construction  process.  All  of  these  systems  share  a  common  data  model  –   that  of  the  construction  facility.  BIM  can  provide  a  common  platform  to  facilitate   efficient  functioning  of  these  systems.    

4.4.4  Fit-­‐out  and  Handover  

4.4.4.1  Visual  feedback  during  fit-­‐out  operations    

During  the  fit-­‐out  operations,  a  significant  number  of  parallel  activities  are  going   on.   The   fit-­‐out   process   can   become   quite   complex   especially   for   projects   such   as   hospital  buildings  where  specialist  machines  have  to  be  installed,  linked  and  tested   before  handing  over  the  facility  to  the  owner.  In  such  situations,  visually  keeping  a  

track  of  the  progress  can  be  quite  useful  to  ensure  efficient  operation.  BIM  can  be   used  to  provide  a  visual  workflow  for  tasks  such  as  –  arrival,  testing,  installation   and   sign-­‐off   of   equipment   and   systems   for   construction   projects.   Tasks   at   a   different   stage   in   the   workflow   can   be   coloured   differently   in   BIM   to   visually   provide  a  feedback  to  the  project  manager.    

4.4.4.2  Digital  handover  with  accurate  as-­‐built  model  

With  BIM  it  is  possible  to  use  technologies  such  as  laser  scanning  to  first  compare   the  actual  construction  with  design  model  and  then  to  provide  an  accurate  as-­‐built   model  of  the  facility.  Laser  scanners  provide  a  “point  cloud”  of  the  3D  geometry,   which   can   be   imported   in   many   popular   BIM   systems   to   then   develop   a   surface   model  that  can  be  overlapped  on  top  of  the  design  model  to  make  comparisons.     Also,   during   the   handover   stage   it   is   also   possible   for   the   contractor   and   subcontractors   to   capture   accurate   information   about   the   building   from   operational  perspective.  For  example,  information  regarding  important  assets  such   as   manufacturing   data,   operational   and   performance   data   and   service   related   information  could  be  captured  for  a  digital  hand-­‐over  to  the  client.  

4.4.5  Operation  and  Maintenance  

An   accurate   as-­‐built   model   that   carries   up-­‐to-­‐date   information   about   a   facility’s   assets  and  its  operational  data  can  be  extremely  useful  to  the  FM  team.  This  has   been  demonstrated  by  the  Maryland  General  Hospital  case  study  (Eastman  et  al.,   2011).   When   the   Facilities   Management   system   is   integrated   with   the   Building   Information   Model,   the   operatives   can   refer   to   hidden   objects   (behind   the   structure)  and  bring  up  relevant  information  to  reduce  time  taken  to  respond  to  a   call.  

4.4.6  Summary  

BIM  can  be  seen  not  only  as  a  technology  or  a  set  of  technological  tools,  but  as  a   process   change   that   supports   the   entire   lifecycle   of   the   construction   project.   It   provides  the  basis  for  new  design  and  construction  capabilities  and  changes  in  the   roles  and  relationships  among  a  project  team.  When  adopted  well,  BIM  facilitates  a   more   integrated   design   and   construction   process   that   results   in   better   quality   buildings  at  lower  cost  and  reduced  project  duration.  (Eastman  et  al.,  2011).