• No se han encontrado resultados

MÓDULO FORMATIVO 4

In document BOLETÍN OFICIAL DEL ESTADO (página 31-37)

BOLETÍN OFICIAL DEL ESTADO

MÓDULO FORMATIVO 4

Since the wind is determined by random meteorological processes, it is inherently variable and,  therefore, wind power presents high variations not only seasonally, but also on shorter time  scales,  namely  on  hourly  basis.  Several  extreme  ramp  rates  of  reduction  on  wind  power  generation were already recorded in Portugal and elsewhere. Additionally, the supply of power  from wind turbines is stochastic in nature and the actual power is more or less proportional to  the third power of the wind velocity. Therefore, wind power cannot be perfectly forecasted  since a small error on the wind velocity leads to a high error on the forecast of the power.  Figure 5.20 presents one example of a recent event (January 6, 2014) with a large ramp rate of  generation reduction and a large forecasting error. In this situation, there is a reduction of 1190  MW (40%) between 13 and 17 hours (average reduction of 300 MW/hour) and simultaneously  there are large errors on the forecast, reaching a maximum error of 29.5% (476 MW).  As far as security of supply is concerned, the most severe problems due to the wind power  intermittence  occur  in  the  peak  load  hours,  since  the  largest  part  of  the  available  system  resources to deal with the intermittence is already used and a sudden reduction of the wind  power  production  can  have  critical  consequences  on  the  system  reliability.  Thus,  instead  of 

acting  in  the  supply  side,  to  avoid  the  most  severe  intermittent  situations,  Demand  Side  Management measures can be promoted to achieve consumption reductions and, mainly, to  balance supply and demand. Therefore, the use of efficient space conditioning solutions is very  important to avoid such problems.  However, in cases of high wind power penetration, the energy consumption reduction during  the peak hours may not be enough, due to the large generation variations, in situations with a  large forecasting error. In such situations it will be very important to have Demand Response  (DR) technologies to “force” consumption reductions at near real time, in the precise moment  in  which  the  critical  situations  occur.  In  a  smart  grid  context  this  can  be  implemented  by  controlling the space conditioning loads, with a change in the temperature of the system or  even with a temporary shutdown.      Figure 5.20: Wind generation and forecast on January 6, 2014.    As it was previously demonstrated for the experimental GSHP installation, the shutdown of the  system  space  conditioning  during  one  hour  can  be  done  without  a  relevant  impact  on  the  comfort level. Therefore, such strategy was implemented by considering the shutdown of the  system between 1 and 2 p.m. The reduction of consumption achieved with the shutdown can  therefore be considered as a virtual increase of the wind generation. Figure 5.21 presents the  achieved  impact  and,  as  can  be  seen,  during  such  period  the  difference  between  the  real  generation  and  the  forecast  can  be  substantially  decreased  (a  reduction  of  55.5%  was  achieved).  This  is  achieved  just  by  controlling  25%  of  the  office  buildings,  and  therefore  by  expanding  this  control  strategy  to  all  office  buildings  and  other  types  of  buildings  a  total  compensation of the error would be possible. 

  Figure 5.21: Impact of DR on the reduction of wind forecasting errors on January 6, 2014.   

The DR action was implemented in the beginning of the variation and not in the moment of the  highest  error,  since  the  main  problems  to  the  electrical  grid  occur  in  the  beginning  of  the  variation, due to the need of a fast answer from the system to compensate the lost generation  capacity.  If  the  system  does  not  have  enough  flexibility  to  react  immediately,  e.g.,  with  the  increase of hydropower generation, it can have critical consequences on the system reliability.  Therefore, concentrating the load reduction in the beginning of the variation, to give enough  time to increase the generation ensured by other sources, is usually the best solution to avoid  major reliability problems. The implementation of DR presents as a main benefit the increase  on the electrical grid reliability, but it can also represent an economic benefit for the consumer,  since the users that accept the implementation of a DR action are usually compensated with a  reduction of tariffs or a payment by each DR action implemented.     

5.5 ‐ C

ONCLUSIONS

 

Using the experimental GSHP system, it was demonstrated that heat pumps, when combined  with the building thermal mass, can be used as a flexible load to balance supply and demand,  and to allow the reduction of operation costs at the consumer side. For this purpose, several  strategies of heating loads management were proposed and tested. 

To  assess  the  thermal  response  of  the  building,  a  model  based  on  the  lumped  capacitance  method  was  applied.  This  model  allowed  determining  the  required  preheating  time  as  a 

function of the building parameters, building unoccupied period, desired indoor temperature,  outdoor temperature and HP thermal power.  

The indoor air temperature decay was analyzed after shutting down the heating system one  hour before the ending of the occupation period. After turning off the system for one hour, the  indoor air temperature only decreased 1 °C (for 1.5 hours the decrease is 1.5 °C). Assuming that  this  temperature  decrease  is  acceptable  for  users,  the  curtailment  strategy  can  be  used  for  periods up to 1.5 hours.  

To guarantee thermal comfort to the users when they arrive and to take advantage from the  lower electricity prices, two preheating strategies were applied. The main purpose is that at 9  a.m.  the  building  temperature  is  near  to  the  steady  state  to  minimize  or  even  to  avoid  the  energy consumption during the morning peak period. Different preheating times were tested,  taking into account the outdoor temperature, associated to a curtailment strategy at the end  of the day and costs savings of 16‐19% were achieved. Higher costs savings can be achieved  (about  34%)  with  longer  preheating  periods  in  order  to  be  possible  to  avoid  energy  consumption during the morning peak, as well as by shutting off earlier the heating system,  one hour before the ending of the working day, to avoid the second electricity peak period.  The  impacts  on  the  national  electric  diagram  of  applying  the  preheating  strategy  and  the  curtailment  strategies  were  assessed.  These  strategies  were  extrapolated  to  other  office  buildings with similar occupancy periods, assuming that only 25% of the office buildings can be  controlled. The preheating strategy of the office buildings was used as a way to integrate the  surplus of renewable energy generation. Based on the two examples studied, it was found that  significant part of the renewable energy generated during night and early morning (19‐30%)  can  be  absorbed.  It  was  also  demonstrated  that  by  shutting  down  temporarily  the  space  conditioning it is possible to substantially compensate the variations of wind power generation  and  forecasting  errors  during  the  first  hour  of  variation  (55.5%  in  the  presented  scenario),  giving enough time to adapt the other resources of the electrical system. 

The role of high efficient heat pumps combined with building thermal mass (as flexible load)  can play a key role for sustainable and efficient building space heating, as well as contribute to  integrate  electricity  generated  by  intermittent  renewable  resources  and  to  improve  grid  management using load leveling and Demand Response strategies. 

   

CHAPTER 

In document BOLETÍN OFICIAL DEL ESTADO (página 31-37)

Documento similar