• No se han encontrado resultados

Nombres de Dominio en general desde la introducción de nuevos gTLD

EnQuest has investigated a range of development options for the following project elements:

1)

Production System

2)

Drilling rig

3)

Production flowlines

These are tabulated below, (Table 3-2) highlighting advantages and disadvantages with respect to technical, economic and environmental considerations.

The FPSO was selected as the best production option. For a small development with a relatively short field life such as Alma, the ability to re-use an existing production facility is a key factor - on both economic and environmental grounds. Having selected the FPSO option, the Uisge Gorm was selected as the most suitable for the following reasons:

 Alma requires a similar mooring configuration and the vessel has previously worked within 15km from the proposed Alma location

ENQUEST HEATHER LIMITED  ALMA FIELD DEVELOPMENT

Recent North Sea service and maintenance records are up to date for recent production operations

Large range of capacity handling

Can install produced water reinjection (PWRI) with minimal oil in water (OIW) discharge, benefiting environment

Potential for a change from diesel power generation, providing environmental improvement

ENQUEST HEATHER LIMITED  ALMA FIELD DEVELOPMENT

REPORT REF: P1459BA_RN2525_REV0 3-6 21/07/2011

Table 3-2: Pros and cons or dif ferent development scenarios

Option Pro Con Decision 1A: FPSO  A limited number of FPSOs are available for deployment

Provides an integrated storage and offloading system Modification required are more economic that other available options e.g. new platform

FPSOs fit for expected field life

Using an existing FPSO is cheaper than a new build FPSOs considered have proven track record in the UKCS Minimal seabed disturbance from installation

Can be easily redeployed at end of field life

 Age of available FPSOs / fatigue life Substantial modifications required

Tanker offloading system potentially higher risk of oil spills than export pipelines

Selected

1B; Petrofac OE&O FPF-1

Readily available

Would provide consistent Duty Holder across all EnQuest Assets Would be suitable for deployment to NNS at end of field life Established contracting strategy with Petrofac Offshore Engineering and Operations (OE&O)

Would require substantial replacement of a number of systems e.g. process system, accommodation and utilities, riser connection system, helideck, primary and secondary steelwork, mooring system

Fatigue and integrity issues

No crude storage / offloading capabilities so would require export routes

Limited pipeline export routes

Rejected

1C: New platform

Systems designed specifically for Field New facility and equipment designed for field life Latest technology designed into build

Definitive build cost Lower OPEX costs

Limited pipeline export routes

Utilisation of existing facility and avoidance of new build environmental impacts

Larger seabed footprint than FPSO

Jacket structure would require substantial piling operations Substantial costs incurred with build and installation Would require decommissioning at end of field life Higher CAPEX

ENQUEST HEATHER LIMITED  ALMA FIELD DEVELOPMENT

REPORT REF: P1459BA_RN2525_REV0 3-7 21/07/2011

Option Pro Con Decision 1D: Subsea

tie-back

No requirement for oil storage

No requirement for tanker mooring and offloading facility Lower OPEX costs associated with tanker

 Avoidance of potential environmental impacts of crude transfer and tanker fuel oil

 Avoidance of known seabed hazards from previous operations in field

Limited opportunities to tie into pipeline export routes. Closest facility is 19km

Would require decommissioning at end of field life

Potentially larger seabed disturbance with longer export route  Additional costs associated with pipeline crossings

Identification of clear pipeline routes difficult due to large amount of seabed hazards from previous production operations Would incur environmental impacts from pipelay trenching and installation vessel activity.

Rejected

2A: Semi- Submersible Drilling Rig

Less weather dependant during positioning on site

More scope for moving rig but maintaining same anchor pattern – less seabed disturbance. For example, moving to allow subsea infrastructure to be installed, moving rig if subsurface philosophy changes, ability to drill six wells on same anchor pattern Easier to run horizontal xmas trees

Better selection options- at least two rigs are known to be available

Current drilling team has extensive knowledge of semi submersible drilling operations

More waiting on weather during operations

Moving to new wellhead location (skidding rig) on same anchor pattern dependent on weather

More expensive day rates

Potentially larger seabed footprint if consider scour marks from anchor catenary as well as anchor mounds

Selected

2B: Heavy Duty Jack-up Drilling Rig

Lower operation day rates

Potentially lower waiting on weather once located on individual well

Potentially smaller seabed footprint (only area of spud cans)

Lower lifting and storage capacity

Movement between individual wellheads is limited and may require full rig move outside of footprint – could lead to greater seabed disturbance that a semi-submersible

Rig availability tighter than for semi-submersibles Spud can disturbance could affect future rig locations

Would require additional geotechnical site investigations for spud can placement which could not be covered under Alma surveys in 2010

Riser tensioning capacity is greater in deeper water Jack-up may experience problems with horizontal xmas trees

ENQUEST HEATHER LIMITED  ALMA FIELD DEVELOPMENT

REPORT REF: P1459BA_RN2525_REV0 3-8 21/07/2011

Option Pro Con Decision 3B: Buried

flowlines (water injection)

Greater protection for flowlines – no additional protection such as rock would be required except for mattressing and grouting at trench transition areas

Conventional / proven solution

Option to surface protect spans which cannot be buried due to existing subsurface obstructions

Larger seabed footprint

If select low temperature option for flowlines then flowlines could not be protected or buried

 As the flowlines would run quite hot, there would be the requirement for large cooling spools if trenched

Harder to decommission would likely leave in-situ at end of field life

Higher mobilisation costs for installation as would need more vessels and equipment

Higher risk of subsurface obstructions during trenching which would need to be micro-routed

Selected

3A: Surface laid flowlines (production)

Ease of installation – range of installation vessels available. Benefit as compact field layout with possible drilling rig on site during installation

Lower mobilisation costs for installation Potential of re-use / decommissioning easier Conventional / proven solution

Risers only solution available with FPSO Minimal seabed disturbance

Lower risk of subsurface obstructions because no trenching

Greater risk of damage Procurement costs

May require dropped object protection e.g. rock material, concrete mattresses which will increase seabed footprint

Less than 1m of silty sand as surface layer. May sink into sand.

ENQUEST HEATHER LIMITED  ALMA FIELD DEVELOPMENT