• No se han encontrado resultados

i. Increased community and stakeholders’ contribution in kind and cash towards the project implementation.

ii. The District Council becomes aware with the project and promised to be close

with project through its youth development section.

iii. The two famous NGOs dealing with environmental conservation in the district

(MKUHUMI and MAJUKUU) visited the project and promised to see how they

can support in future.

Objective 3: To implement Sustainable Charcoal Project to reduce youth unemployment

problem in Chanzuru ward by the end of July 2013.

5.3.9 Situation being Addressed

A large number of jobless youth and who are not aware of what to do as a lack of

employment opportunity.

This situation prevails in almost all the wards in Kilosa District. This was evidenced by

the large number of youth who are complaining about unemployment problem It was

very unfortunate that youth in Chanzuru are surrounded by various opportunities as

identified during resources mapping but they were not aware of such opportunities and

the means to exploit it. Instead they are thinking of a formal sector as the only

5.3.10 The Process the Project Initiated.

After resource mobilisation, the stakeholders engaged in implementation of Sustainable

Charcoal Project to reduce youth unemployment problem.

5.3.11 Changes Noted during the Evaluation

As the results of the processes that the project initiated, the following changes have been

noted in relation to the success indicators;

After the implementation of the project at phase one (supply of necessary facilities/

equipments) for production of sustainable charcoal twenty youth from three youth

economic groups shown interest to start the project. It is expected more youth will join

the project because the limit number per group is fifteen (15) members per group,

however for management purposes it is agreed the groups to start with less the ten (10)

members per group at the beginning.

The evaluation team also observed that , Youth development Section in the district to be

in close collaboration with WDC through WEO to ensure sustainability of the groups

and to make sure they implement the intended project as per plan and promised to

provide some technical support especially in the area of book keeping and group good

governance. This ensures the project sustainability as the owners have planned the

operational maintenance.

The review of documents including implementation and monitoring plans, monitoring

tools and project budget were also done by the Evaluation Team. Nevertheless, the

documentary review findings revealed that;

i. The implementation plan was availed and prepared well, although it was revisited

Section and WDC In August 2013 due to seasonality problem and un received

training funds from REA.

ii. The project was bit expensive, nevertheless the collected resources and funds from

stakeholders were wisely utilised. It was also observed that there was a good record

keeping and proper use of internal control systems.

iii. The participatory monitoring and evaluation systems were in place and used.

iv. In general, the team revealed that project objectives were achieved in spite of the fact

that number of few activities such as training and community awareness creation in

two sub villages of Idete and Mfululi is still going on. It was also noted that there

was strategy of accomplishing remained activities that was planned to complete by

the mid August 2013.

(b) Challenges

While the project has made a significant achievement in improving the community

awareness on youth problems and measures to be taken to overcome such problems,

however some challenges were noted in some areas that obstructed the full achievement

of the project objectives as highlighted below:

i. It was observed that the time given for the implementation of the project that

demands community contribution was short. Also the period between January

and June communities of Kilosa District whom majority of them are agro

pastoralists are normally busy with farm activities and thus low contribution to

the development projects.

ii. Young people have a lot of special needs that also tried to confuse the project

iii. High expectation of youth was also another challenge. It was not easy to fulfil

their high expectations.

iv. Lack of awareness on the rights. Both youth male and female were not aware on

their rights; however female youth are more affected by lack of awareness

comparing with male.

v. Lack of awareness on National Youth Development Policy of December 2007

and Employment Policy of 2008 and SME Policy of 2003 and other related

documents among youth

vi. Poverty among the youth and their families

vii. Lack of clear system for monitoring youth data and public infrastructures to suit

the needs of youths.

(c) Lessons learnt about what worked and what did not work

From the experience of Sustainable Charcoal Project to reduce youth unemployment

problem, lessons drawn include;

i. Active participation of youth in the projects affecting their life is very

important since it makes them to fill being valued. In Kilosa District young

people were not actively participating in decision affecting their lives.

ii. Youth have the capacity of doing various activities what they need is just

enabling environment.

iii. Many youth have a lot of problems ranging from poverty to social stigma.

iv. Implementation of project that concern with charcoal briquette that depends

on community contribution during the rainy season is very difficult.

v. Youth deserve right being supported when implementing their ideas through

vi. Investment in Youth development can help in national economic growth and

prevent youth from harmful behaviour.

Documento similar