Shipping & delivering to site:

Materials and equipment transportation is an extremely delicate task and requires extensive planning. Adequate planning includes consideration of:

• Insurance coverage; • Proper packing;

• Local and foreign custom requirements; • Lead times;

• Cost analysis;

• Local transportation to site capabilities; • Local traffic restrictions;

• Project schedule required delivery dates; • Financial implications; and

• Temporary storage arrangements.

Project Procurement Financial Implications

The cost of project material and equipment represent an important part of the total budget, big enough to cause serious financial damage if good cost control is not exercised.

Decision-making for procurement organizations essential role in project management is based on:

• Purchase records; • Specifications files;

• Vendors' performance records; • Price historical information; and • Exhaustive research.

With today's computer aids these tasks have become less of a load for the purchasing organizations and quick management information related to purchasing requirements data may be retrieved from data files if they are kept adequately updated. Projects cash flow are very much concern with timely acquiring materials and equipment and avoiding

unnecessary expenses tied to transportation expediting or temporary storage. The

procurement organization purchasing plan must follow the construction approved schedule and its periodic revisions.

Material procurement has to be concerned with: • Market studies;

• Trend analysis; • Make-or-buy studies; • Price-cost analysis;

• Supply sources investigation; • Value analysis;

• Value engineering analysis;

• Latest purchasing innovations; and • Computer advances.

Only then, it will be able to provide management support in its financial decision-making activities.

Procurement Engineering Value Analysis

Procurement engineering value analysis is a disciplined examination of the project procurement requirements to eliminate unnecessary costs brought up by:

• Over design;

• Lack of original ideas; • Insufficient information;

• Temporary business pressures and the like.

Value is defined as the relationship between price and worth of the function of a particular element.

Value = price / worth

The primary concern of any design is the function. Too frequently, the subject of cost is pushed into the background and then forgotten. A value engineering program will not let the team forget about cost and it will generate a healthy relationship between function and cost.

Value engineering may be applied to the procurement functions as follows:

1.-Set up a plan.

Before starting any procurement activity, ascertain that the procurement team has a plan of action. Follow the value engineering plan approach by breaking down the plan in phases as follows: • Feasibility; • Information; • Creativity; • Evaluation; • Proposal; and • Implementation.

2.- Get all the facts.

Become familiar with the procurement elements by factually reviewing them. Find answers to the following questions:

• What is the lead time required for fabrication? • How many units will be needed?

• When are the units needed? • How many suppliers are there? • How much does it cost?

3.-Know about costs.

To make a complete analysis of any procurement element, it is essential to know not only the total cost, but the breakdown of the total cost. This breakdown should include logistics, trade trends and the like.

4.- Set a currency value on each main idea.

Rank your cost reduction ideas and start working on those offering a better return.

5.- Update your information continuously.

Keep good information about vendors’ activity and materials market developments. Participate in procurement related professional associations for they are continuously updating information and presenting new approaches and ideologies.

Procurement and IT

Purchasing and materials management is one of the project areas that have benefited most from the introduction of sophisticated yet easy to master computer applications.

Computers applications have brought along: • Reduction of paper work; • Ready access to collected data; • Communications improvement;

• Fast response to changes in purchasing variables; • Automated data analysis;

• Virtual elimination of filing; and • A host of other intangible benefits.

Some specific project procurement tasks improved due to computer activity are:

At project proposal phase:

Creating and maintaining vendors' data, creating and maintaining quotations' data, evaluating suppliers, reviewing quotations, processing planned items requirements, generating cash requirement reports, maintaining a master data base, and generating materials take-offs.

At preconstruction phase:

Computers technological advances are helping at generating requisition and purchase orders, reviewing and approving requisitions, updating cash flow requirements, monitoring and controlling suppliers, and monitoring project management interface.

At construction phase:

Altering purchasing orders, answering order inquiries, estimating time of arrival, closing purchase orders, updating historical data bases, consolidating cash flow requirements, and providing instant information and communication

Additionally, computers provide real time processing capabilities. The new available data is entered on line into the computer and information systems are updated forthwith. Computers hardware configuration may be designed according to the customer needs and expanded as business expand without losing flexibility, quality or money.

Software is found galore for all kind of business activities or may be designed in-house following friendly, easy-to-learn, powerful, computer languages. Computers have changed the face of materials management and procurement activities as much as they have done with any other business.

Vital functions as statistical information for the formulation of purchasing policy, can be updated as new data is entered and reported as:

• Historical purchasing activity; • Prices variance;

• Purchasing order analysis and evaluation; • Purchasing evaluation by vendor;

• Vendors’ delivery records; • Purchasing economic indicators; • Purchasing backlog;

All of the above mentioned are always available and revised to the latest trends thanks to computers. Computers let you sort your information, summarize it, break it down into components, present it in alternate formats, and highlight business most relevant areas at incredible speeds.

Procurement Measurement

Normally for a major project, the procurement of long lead technical equipment and

materials is a function of the engineering effort and it is included in the engineering budget as a separate item.

The procurement effort consists of three major functions: • Material Take-offs;

• Purchase Requisitions; and • Purchase Orders

To measure physical progress of the procurement effort, each of the three major

procurement functions should be weighted as a percentage of the total procurement effort. This weight factor should be based on the budgeted man-hours for each function relative to the budgeted man-hours for the total procurement effort as shown in the table below.

FUNCTIONS ESTIMATED QUANTITIES ESTIMATED MANHOURS FUNCTION % WEIGHTED VALUE MAT. TAKE-OFF 150 400 26.6 PR’s 200 700 46.7 PO’s 100 400 26.7 Procurement 100 Material Take-offs

Physical progress measurement for material take-offs is based on the estimated number of drawings requiring material take-offs versus the number of drawings for which take-offs have been completed.

For example:

The estimated drawings requiring take-offs = 150 Drawings with take-offs complete = 75 Physical progress would be: (75/150)(100) = 50%

Purchase Requisitions

Physical progress measurement for purchase requisitions is based on the estimated total number of purchase requisitions versus the number of requisitions approved for purchase. For example:

The total estimate of Purchase Requisitions = 200 Purchase Requisition approved for purchase = 50 Physical progress would be: (50/200)(100) = 25%

Purchase Orders

Progress should be based on both the quantity of purchase orders placed and the

cumulative dollar value of materials shipped from the manufacturer's plant (explanted). The quantity of purchase orders placed will contribute 50 percent progress and the dollar amount of total material value explanted will contribute the remaining 50 percent.

For instance, the purchase order quantity is 100 with 28 purchase orders placed. The total cost of purchase materials is estimated at 50 million dollars and from this amount

approximately 1 million dollars of materials has been explanted. Progress would be calculated as follows:

28 PO's placed out of 100 = 0.28( 0.5 )100 = 14%

$ 1 MM of materials explanted out of $50MM= 0.02 x 0.5 (100) = 1% Progress to date for purchase orders:

14+1=15%

Total Procurement Progress

By evaluating the physical progress of each major procurement function, the total procurement progress can be determined as shown in the table below.

FUNCTIONS PERCENT

COMPLETE

WEIGHTED VALUE PROCUREMENT

CONTRIBUTION