• No se han encontrado resultados

La Retórica como ciencia de la comunicación en la antigúedad

In document UNIVERSIDAD COMPLUTENSE DE MADRID (página 50-76)

The project’s potential impacts and their significance have been assessed using the methodology described in Section 7.2 above. A summary of these impacts and their significance is presented in Table 6.

Table 6: Potential Impacts and Their Significance Impact Phase Sensitivity Magnitude Significance Prior

to Mitigation Mitigation and Enhancement Measure Residual Significance Environmental impacts due to project siting:

Changes in physiography and landform All phases Mild Major Moderate adverse Development and implementation of a Landscape and Replanting Plan in the project footprint areas

Low adverse Change in land use (3,900 ha) t

Pre-construction, Construction

Severe Major High adverse Compensation and assistance to affected households and communities according to eligibility matrix of RAP

Implementation of landscaping and plantation plan

Low to moderate adverse Loss of natural vegetation and trees

Pre-construction, Construction

Mild Medium Moderate adverse Planting of native trees near resettlement villages and along roads

Promoting the use of alternatives to fuel wood

Afforestation and Forest Rejuvenation Plan

Low to Moderate Adverse Inundation of 33 mosques in affected villages

Pre-construction, Construction

Severe Medium High adverse Disassembling and rebuilding of five wooden mosques in new resettlement villages at higher elevations, as discussed and agreed with the communities.

Replacement of remaining 28 mosques with the new ones in resettlement villages.

Minimal

Impact of increased traffic and transportation on KKH

All phases Severe Medium High adverse Traffic Management Plan, including awareness raising and safety measures

Major Critical Realignment and construction of 62 km of new KKH at higher level

Minimal Loss of bridges and access roads connecting

villages on right bank

All phases Severe Major High adverse Building of a new suspension bridges over the reservoir and construction of new access roads along the right bank

Minimal Adverse impacts on natural habitat All phases Severe Major High adverse Study, selection and implementation of minimum two

community-led conservation activities in the DHP sub-catchment areas

Supporting and promoting conservation activities in Kaigah game reserve

Compensation of community for any losses from sales of hunting permits during construction stage

Moderate to high adverse

Social impacts due to Project Siting:

Change in land use (3,900 ha) Pre-construction and construction

Severe Major High adverse Prepare and implement RAP; temporary lease of land needed for construction facilities

Severe Major High adverse Compensation and assistance to affected households and communities according to eligibility matrix of Resettlement Action Plan

Moderate to high adverse

Relocation of shops/commercial establishments

Pre-construction,

Mild Medium Moderate adverse Compensation for lost assets and commercial enterprises

Assistance and livelihood restoration of affected persons

Low to moderate

Impact Phase Sensitivity Magnitude Significance Prior

to Mitigation Mitigation and Enhancement Measure Residual Significance

Construction according to RAP adverse

Loss of civic amenities

Pre-construction, Construction

Mild Medium Moderate adverse Rebuilding of civic amenities by project Minimal

Loss of 143 ha agricultural land and 280 ha grazing land

Pre-construction, Construction

Severe Medium Moderate adverse Compensation for lost land, crops and fruit trees and livelihood assistance according to RAP

Implementation of Income and Livelihood Restoration Plan and Area Development and Community Support Program

Moderate to high adverse

Increased pressure on high altitude forests and grazing areas

All phases Mild Medium Moderate adverse Forest management plan, including forest rejuvenation Moderate adverse Impacts of construction of 132 kV power supply

line for project and colony

Pre-construction Construction

Mild Medium Moderate adverse Compensation of owners of land

Avoiding residential and agricultural areas and dense forest

Reduction of health hazards for community and workers

Minimal

Generation of sustainable employment Construction and Operation

Mild Medium Moderate beneficial  Fixed quota for local workers and technicians

 Vocational training; monitoring of labor rights, workforce composition, working and living conditions

High beneficial Increased economic activity All phases Mild Medium Moderate beneficial  Establishment of new businesses and commercial enterprises;

local employment

Moderate beneficial Environmental Impacts during Construction:

Increased traffic on KKH and local access roads Construction Severe Medium High adverse Traffic Management Plan, including awareness raising and safety measures

Low adverse Impacts on Kaigah Community-managed Game

Reserve

Construction Severe Medium High adverse Monitoring of noise levels during the quarry operation

Reduction of duration, timing and strength of blasting operations and vibrations according to internationally recognized standards

Use of Kaigah quarry only for borrowing material for dam construction and construction of the new KKH section (limited period)

Control of access to the reserve area for workers and public in cooperation with the community

Awareness raising of workers, employees and general public regarding the importance of this area

Moderate adverse

Impact on river habitat due to construction activities and drying of river section between two coffer dams

Construction Mild Medium Moderate adverse Control of waste water and sediment releases to river

Water quality management protocols in ECPs

Studies to improve aquatic baseline data; monitoring

Low adverse

Fish entrainment and mortality Construction and Operation

Mild Minor Low adverse Protection measures at inlets of tunnels to deter movement of fish

Low adverse Potential risk air, noise, soil and water pollution

by construction works

Construction Medium Medium Moderate adverse Pollution Prevention Plans to be prepared by Contractor

ECP plan by Contractor

Minimal Risk of pollution from solid waste and waste

effluents

Construction Mild Medium Moderate adverse Waste Disposal and Effluent Management Plan

ECP by Contractor

Minimal

Impact Phase Sensitivity Magnitude Significance Prior

to Mitigation Mitigation and Enhancement Measure Residual Significance Loss of land in disposal areas Construction Low Minor Minimal Re-use plan for rock material

Disposal Area Management and Restoration Plan

Minimal Impacts of noise and dust from construction,

traffic and use of explosives

Construction Severe Medium High adverse No blasting during night time

Awareness raising and grievance mechanism

Minimal Increased risk of landslides Construction

and Operation

Severe Medium High adverse Permanent monitoring in construction areas

Preventive measures in high alert areas

Emergency Preparedness Plan

All phases Mild Minor Moderate adverse Use of non-wood fuel for cooking and heating

Improvements to community forestry management

Code of conduct for workers and employees

Awareness raising for workers and protection of flora and fauna

Moderate adverse

Risk of water pollution of storage tanks in reservoir area

Construction Mild Minor Low adverse Removal of oil tanks and other potential sources of pollution from reservoir area

Minimal Shortages in local water supply and sanitation in

residential areas

Construction Mild Medium Moderate adverse Drinking Water Supply and Sanitation Plan to be prepared by Contractor independent from local domestic services

Mild Medium Moderate adverse Landscaping plan; establishing nurseries

Plantation of trees conditions and health risks for workforce

Construction and Operation

Severe Medium High adverse Traffic Management Plan addressing general access

Safety and security actions and procedures to protect local community

Occupational Health and Safety Plan to be implemented

Emergency Preparedness Plan; Contractor follows IFC Performance; Standards on Labor and Working Conditions;

Safety training for workers

Severe Major High adverse Awareness campaign

Development of Migration Management Plan

Grievance mechanisms to address complaints

Minimal

Conflict due to inpparopriate behavior by workers

Construction and Operation

Mild Medium Moderate adverse Awareness campaign; Code of conduct for workers

Grievance mechanism

Minimal Reduced safety and health risks by interaction of

workforce with local residents

Construction and Operation

Mild Medium Moderate adverse Public Health Action Plan

Safeguards and awareness raising against communicable diseases

Minimal

Increased load on local services and supplies Construction Mild Medium Moderate adverse Contractor to procure camp supplies in a manner not affecting availability of essential commodities

Minimal Environmental impacts during Operation and Maintenance:

Impact on 571 ha of aquatic habitat along Indus and its tributaries in reservoir area

Operation Mild Medium Moderate adverse Developing of fish hatchery with native snow carps for stocking fish in the affected tributaries and reservoir

Monitoring of spawning areas

Low to moderate adverse

Impact Phase Sensitivity Magnitude Significance Prior

to Mitigation Mitigation and Enhancement Measure Residual Significance

Monitoring programs Impacts of first filling of reservoir on safety of

people and livestock and stability of slopes

Operation Severe Major High adverse Awareness campaign and warning signs

Slow rate (1 m/day)

Permanent monitoring of slopes

Minimal

Barrier effect to fish migration Operation Mild Medium Moderate adverse Compensatory fish hatchery

Study of fish migration; establishment of baseline data

Low to moderate adverse Reduced water flows between dam and tailrace

(4.4 km) during low flow season

Operation Very Severe

Major Critical Release of 20 m3/s of environmental flow from dam and 222 m3/s from tail race

Downstream monitoring and adjustment of flows if required

Moderate to high adverse Impact on downstream and aquatic habitats and

fish due to changes in water flows and quality (temperature, DO, sedimentation)

Operation Mild Medium Moderate adverse Monitoring of downstream water quality and aquatic habitats Low to moderate adverse Impact of sedimentation on reservoir area Operation Severe Medium High adverse  Yearly flushing after 10-15 years of operation

 Reduction after completion of DB dam

Low adverse

Impact of daily reservoir operations during base-load operation

Operation Mild Moderate Moderate adverse Fish Conservation and Management Plan

Monitoring and study

Low adverse Impact on downstream fish and fisheries during

flushing operation

Operation Severe Major High adverse Flushing during high flow season (not in low flow/winter)

Development of ramp down criteria (5-10 cm/hr)

Monitoring dissolved oxygen and temperature in reservoir and de-stratification or simultaneous release of water from LLOs and spillways if required

Downstream monitoring of fish, habitats and sediments

Moderate to high adverse

Impact on downstream fish and fisheries due to changes in hydrological flows due to peaking operations

Operation (Post DB)

Mild Medium Moderate adverse Continuous operation of one turbine

Using remaining flow for peak operation

Low adverse

Risk of bird collision and electrocution with transmission cables

Construction and Operation

Mild Medium Moderate adverse Carrying out of avian risk assessment

Maintaining 1.5 meter spacing between energized

components and grounded hardware; covering energized parts and hardware

Installing visibility enhancement objects such as marker balls, bird deterrents, or diverters

Low adverse

Social impacts during Operation and Maintenance:

Creation of large number of employment opportunities through reservoir fisheries

Operation Severe Major High beneficial  Fish Conservation and Management Plan

 Employment of local people

Beneficial

In document UNIVERSIDAD COMPLUTENSE DE MADRID (página 50-76)