CÓDIGO DE LA NIÑEZ Y LA ADOLESCENCIA
2. Aspectos Generales de la Migración
2.1 Antecedentes Histó
2.2.1 Se debe distinguir entre:
The Member States that follow the PSR process to periodically take stock of the safety condition of the plant will find the task of justifying LTO easier if they have implemented a systematic approach to plant ageing management. A good AMP conducted from day one in the service life of a plant is an assurance that the plant will be in its best possible condition and will require a minimum number of changes at the time of its PSR submission for longer term operation, which usually requires more demanding justifications for continuing operation than regular PSRs. The plan of action shown in Fig. 12 illustrates a systematic phased approach developed by the Swedish Radiation Safety Authority for its operators to adequately justify continuing operation for a period longer than first postulated in the original design. This methodology has proven successful in the preparation of the PSR submission for longer term operation.
The blocks at the top of Fig. 12 represent the preparatory phase prior to the LTO safety review submission.
The middle blocks denote the LTO assessment phase. In this phase, nuclear power plant operators are required to verify that their AMP is adequate. They conduct this verification through an ageing management review in which
they ensure that the original component design that has operating time limitations is verified for the new intended time of operation (e.g. 60 years). This verification is referred to as TLAA.
In keeping with IAEA Safety Guide publication on Ageing Management for Nuclear Power Plants (NS-G-2.12) [1], paragraph 2.5, and Safety Reports Series No. 57 [15], section 5.3, the regulator in Sweden requires that plant ageing be managed proactively, by coordinating existing programmes such as maintenance, ISI, surveillance, operation programmes, technical support programmes (including analysis of ageing mechanisms) and R&D. Ageing management should be a cross-cutting programme that provides a methodological process to detect and mitigate material degradation. This process should be used as part of the justification for safe LTO.
The blue block at the centre of Fig. 12 represents the proactive review effort of the AMPs of all passive SSCs, singled out by the screening process and grouped by major systems and engineering disciplines. All existing maintenance and surveillance programmes are checked for LTO acceptability, as represented by the yellow box on the left. The blocks to the right of the central blue box represent the typical major LTO projects being assessed for LTO and for which TLAAs are produced to qualify components, subcomponents and subsystems requiring it in each of the major LTO projects. Out of this assessment phase, a number of changes and upgrades are recommended and eventually committed.
The lower blocks in Fig. 12 represent the implementation phase of the committed changes. The figure shows how Sweden’s nuclear regulatory framework integrates IAEA recommendations within the PSR process [12].
It should be noted that during the plant wide scoping and screening process, all relevant SSCs are considered.
However, during the review of the plant AMP in the following stage of the process, only the long lived or hardly replaceable passive structures and components are considered.
Another model, shown in Fig. 13, was developed in the context of the Chinese licensing framework and national standard that requires a safety review submission for operation beyond the period first postulated in the original design.
Figure 13 represents a systematic ageing management model, provided by Qinshan phase 1 nuclear power plant in Zhejiang Province, China. The model includes an overall AMP and a series of topical and equipment specific AMPs. The overall AMP model deals with general aspects of ageing management at the plant level, such
LTO demonstration
Phase prior to LTO assessment
(SRS 57, fig1)
Documentation of basis for LTO
Civil / structural Feasibility
Verification of preconditions
Scoping Screening
IAEA SafetyReport Nr 57 safe long term operation of nuclear power plants
IAEA IGALL International Generic Ageing
Lessons Learned
IAEA
guidelines Regulatory framework
IAEA-SRS-57 Active
Check of existing maintenance and surveillance
programmes
Electrical and I&C Mechanical
Primary system
AMR passive SCs
Regulatory oversight Phase LTO
approval &
implementation (SRS 57, fig1)
Implementation of plan commitments
for LTO RPV Fatigue LBB Underclad
cracks CASS
TLAAs
RPV internal vibration Fatigue crane
cranes Flywheel HCFsteam generatur tubes
EQ Containment
tendons Concrete creep
Thermal ag martensitic
PSR
Phase LTO assessment (SRS 57, fig1)
FIG. 12. Plan of approach for LTO projects (Swedish Radiation Safety Authority). AMR — ageing management review; CASS — cast austenitic stainless steel; EQ — equipment qualification; LBB — leak before break; SC — structure and component.
as plant policies, organizational structure, division of responsibilities, resource allocation, screening of ageing management equipment and identification of significant ageing mechanisms, among others. The equipment specific AMPs cover ageing management procedures for structures or components selected in the screening process.
The AMPs define the ageing issues, the plan and the work scope, including the ageing mechanism analysis, the inspection programme, data collection, the ageing assessment, corrective actions for ageing mitigation and record keeping, among others. The topical AMPs focus on ageing issues across the plant by topic, such as FAC, SCC and obsolescence, among others. The systematic AMP model also includes the development of an ageing management database to be merged with the general plant information system. PSRs can be used to improve, as well as to evaluate, the plant AMP system. In the PSR cycles, the AMP system is reassessed based on the PSR guidelines, potential weaknesses are identified and recommendations are made for further improvements.
When a design upgrade is deemed necessary to enhance safety or performance for an LTO submission, there is a process to assess the project (see Fig. 14). From right to left, first a screening or clustering step is undertaken to review all issues, namely the native LTO issues, the pre-existing proposed improvement projects, which may or may not have LTO implications, and the non-LTO issues. A selection of the issues to be addressed in an LTO submission is undertaken based on a safety impact assessment and expert judgement supported by probabilistic insights (if available). The list of possible changes is consolidated and a short list of LTO issues is included in
Overall AMP Previous PSR
AMP organization and responsibilities
Equipment specific AMPs Equipment screening
Degradation mechanisms
Ageing detection
Ageing mitigation
Ageing assessment
Amp procedures
Degradation mechanisms
Ageing detection
Ageing mitigation
Ageing assessment
Amp procedures
Degradation mechanisms
Ageing detection
Ageing mitigation
Ageing assessment
Amp procedures
New PSR Life extension
Topic for FAC
Investigation
Detection
Mitigation
Assessment
AMP procedures
Review of existing programs and procedures
Topical AMPs
Topic for SCC
Investigation
Detection
Mitigation
Assessment
AMP procedures
Topic of obsolescence
AMP for T1
AMP for T2
AMP for Tn
AMP for RPV
AMP for steam generator
AMP for En
FIG. 13. Systematic ageing management model for Qinshan-1, China. En — engineering; SG — steam generator; T — topic 1; T —
the PSR submission to the regulatory body for an LTO permit. A cost–benefit analysis is also conducted on all consolidated issues and is to include the proposed improvements in a feasibility study, which requires an estimate of the safety benefits. All inputs are then collected and an integrated assessment is conducted. The process eventually leads to an improvement plan, which includes both the short listed LTO drivers and the work plan containing the approved design upgrades.