UNIVERSIDAD NACIONAL DE LOJA
4. Regulación emocional._ control de las emociones que incluye la habilidad para distanciarse de una emoción, la habilidad para regular las emociones en uno mismo y en
1.4 Teorías de las emociones
1.4.3 Teoría cognitiva de la emoción de Schachter
Victor Valley College Project H2 Environmental Consulting Services
Remediation Specifications Project Closeout-Asbestos Abatement 1 PART 1 - GENERAL
1.1 RELATED DOCUMENTS
1.1.1 Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification sections, apply to work of this section.
1.2 SUMMARY
1.2.1 This Section specifies administrative and procedural requirements for project closeout, including but not limited to:
A. Inspection procedures.
B. Project record document submittal. C. Submittal of warranties.
D. Final cleaning. 1.3 DESCRIPTION OF REQUIREMENTS
1.3.1 Definitions: Project closeout is the term used to describe certain collective project requirements, indicating completion of the Work, that are to be fulfilled near the end of the Contract time in preparation for final acceptance and occupancy of the Work by the Owner, as well as final payment to the Contractor and the normal termination of the Contract.
A. Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16.
B. Time of closeout is directly related to "Substantial Completion"; therefore, the time of closeout may be either a single time period for the entire Work or a series of time periods for individual elements of the Work that have been certified as substantially complete at different dates. This time variation, if any, shall be applicable to the other provisions of this section. 1.4 PREREQUISITES TO SUBSTANTIAL COMPLETION
1.4.1 General: Complete the following before requesting the Owner's Representative to inspect for certification of substantial completion, either for the entire Work or for portions of the Work. Include list of known exceptions.
A. In the progress payment request that coincides with, or is the first request following, the date completion is claimed, show either 100% completion for the portion of the Work claimed as "complete", or list incomplete items, the value of incomplete work, and reasons for the Work being incomplete. B. Include supporting documentation for completion as indicated in these
PROJECT CLOSEOUT-ASBESTOS ABATEMENT
Victor Valley College Project H2 Environmental Consulting Services
Remediation Specifications Project Closeout-Asbestos Abatement C. Submit a statement showing an accounting of changes to the Contract
Sum.
D. Advise Owner of pending insurance change-over requirements.
E. Submit specific warranties, workmanship/maintenance bonds, maintenance agreements, final certifications and similar documents. F. Obtain and submit releases enabling Owner's full, unrestricted use of the
Work and access to services and utilities. Where required, include occupancy permits, operating certificates and similar releases.
G. Submit record drawings, maintenance manuals, damage or settlement survey, and similar final record information.
H. Complete final cleaning up requirements, including touch-up painting of marred surfaces.
I. Touch-up and otherwise repair and restore any damages to finishes, floors, walls, or any other item or fixture which is the result of Contractor's actions.
1.4.2 Inspection Procedures: Upon receipt of Contractor's request for inspection, the Owner's Representative will either proceed with inspection or advise Contractor of unfulfilled prerequisites.
A. Following initial inspection, Owner's Representative will either prepare the certificate of substantial completion, or will advise Contractor of work which must be performed before the certificate will be issued. The Owner's Representative will repeat the inspection when requested and when assured that the Work has been substantially completed.
B. Results of the completed inspection will form the initial "punch-list" for final acceptance.
1.5 PREREQUISITES TO FINAL ACCEPTANCE
1.5.1 General: Complete the following before requesting the Owner's Representative's final inspection for certification of final acceptance, and final payment as required by the General Conditions. List known exceptions, if any, in request:
A. Submit the final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required. B. Submit an updated final statement, accounting for final additional changes
to the Contract Sum.
C. Submit a certified copy of the Owner's Representatives final punch-list of itemized work to be completed or corrected, stating that each item has been completed or otherwise resolved for acceptance and has been endorsed and dated by the Owner's Representative and Owner.
PROJECT CLOSEOUT-ASBESTOS ABATEMENT
Victor Valley College Project H2 Environmental Consulting Services
Remediation Specifications Project Closeout-Asbestos Abatement D. Submit consent of surety.
1.5.2 Re-inspection Procedure: The Owner's Representative will re-inspect the Work upon receipt of the Contractor's notice that the work, including punch-list items resulting from earlier inspections, has been completed, except for these items whose completion has been delayed because of circumstances that are acceptable to the Owner's Representative.
A. Upon completion of re-inspection, the Owner's Representative will either prepare a certificate of final acceptance, or will advise the Contractor of work that is incomplete or of obligations that have not been fulfilled, but are required for final acceptance.
B. If necessary, the re-inspection procedure will be repeated at the expense of the contractor.
1.6 RECORD DOCUMENT SUBMITTALS
1.6.1 General: Specific requirements for record documents are indicated in the individual sections of these specifications. Other requirements are indicated in the General Conditions. General submittal requirements are indicated in "submittals" sections.
A. Do not use record documents for construction purposes; protect from deterioration and loss in a secure, fire-resistive location; provide access to record documents for the Owner's Representative's reference during normal working hours.
1.6.2 Record Drawings: Maintain a record set of blue or black line white-prints of contract drawings and shop drawings in a clean, undamaged condition. Mark-up the set of record documents to show the actual installation where the installed work varies substantially from the work as originally shown. Mark whichever drawing is most capable of showing the actual "field" condition fully and accurately; however, where shop drawings are used for mark-up, record a cross-reference at the corresponding location on the working drawings. Give particular attention to concealed work that would be difficult to measure and record at a later date. A. Mark record sets with red erasable pencil and, where feasible, use other
colors to distinguish between variations in separate categories of work. B. Mark-up new information which is known to be important to the Owner, but
for some reason was not shown on either contract drawings or shop drawings.
C. Note related change-order number where applicable.
D. Organize record drawing sheets into manageable sets, bind with durable paper cover sheets, and print suitable titles, dates and other identification on cover of each set.
1.6.3 Record Product Data: Maintain one copy of each product data submittal. Mark these documents to show significant variations in the actual Work performed in comparison with the submitted information. Include both variations in the products
PROJECT CLOSEOUT-ASBESTOS ABATEMENT
Victor Valley College Project H2 Environmental Consulting Services
Remediation Specifications Project Closeout-Asbestos Abatement as delivered to the site, and variations from the manufacturer's instructions and recommendations for installation. Give particular attention to concealed products and portions of the Work which cannot otherwise be readily discerned at a later date by direct observation. Note related change orders and mark-up of record drawings and specifications.
A. Upon Completion of mark-up, submit complete set of record product data to the Owner's Representative for the Owner's records.
1.6.4 Record Sample Submittal: Immediately prior to date or dates of substantial completion, the Contractor will meet at the site with the Owner's Representative and the Owner's personnel, if desired, to determine which, if any, of the submitted samples that have been maintained by the Contractor during progress of the Work, are to be transmitted to the Owner for record purposes. Comply with delivery to the Owner's sample storage space.
1.6.5 Miscellaneous Record Submittals: Refer to other sections of these specifications for requirements of miscellaneous record-keeping and submittals in connection with the actual performance of the Work. Immediately prior to the date or dates of substantial completion, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for continued use and reference. Submit to the Owner's Representative for the Owner's records.
2 PART 2 - PRODUCTS (Not Applicable.) 3 PART 3 - EXECUTION
3.1 FINAL CLEANING
3.1.1 General: Special cleaning requirements for specific units of Work are included in the appropriate sections of Division 2 through 16. General Cleaning during the regular progress of the Work is required by the General Conditions and is included under section "Temporary Facilities".
3.1.2 Cleaning: Provide final cleaning of the Work at the time indicated. Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit of work to the condition expected from a normal, commercial building cleaning and maintenance program.
A. Clean light fixtures and lamps which have been affected by the work so as to function with full efficiency. Replace lamps where inoperable.
3.1.3 Removal of Protection: Except as otherwise indicated or requested by the Owner's Representative's, remove temporary protection devices and facilities which were installed during the course of the work to protect previously completed work during the remainder of the construction period.
3.1.4 Compliances: Comply with safety standards and governing regulations for cleaning operations. Do not burn waste materials at the site. Do not bury debris or excess materials on the Owner's property. Do not discharge volatile or other harmful or dangerous materials into drainage systems. Remove waste materials from the site and dispose of in a lawful manner.