• No se han encontrado resultados

TRAVEST ISMO

In document SANTO DOMINGO IS BURNING Johan Mijail (página 32-48)

 

Inspection Manual/Section‐5/Specific Requirements‐2 (Drums & Vessels)   Page 2‐1 

Section ‐5 

Vessels & Drums   

Specific requirements  2. Specific Inspection Requirements for Vessels   

This section covers the specific inspection requirements of the pressure vessels without the special  purpose internal structures like treys, down comers, or catalyst beds. The text in this section can be   used for the internal and external inspection of the types of vessels including but not limited to  Drums, Flash tanks, LPG Bullets, Two phase and Three phase Separators, sludge catchers,  deaerators, and steam drums etc.  

The coverage of the inspection in this procedure is limited to the first flange, either blinded or  connected with the attached piping. Past the first flanged connection the inspection of piping should  be performed according to the requirements of Section 5 Para 9 of this manual. The inspector  should consult the design details, operation parameters, history of operational upsets, and the  previous inspection reports before commencing the inspection.  

It is the responsibility of the inspector to make sure all of the minimum safety requirements as per  section‐4 of this manual and any additional requirements specific for the vessel being inspected are  in place. Additional safety requirements as deemed necessary must be adopted. 

 

2.1. External Inspection   

2.1.1. Support Structure:   

 

The support structure should be inspected as per the General requirements Para 1.4. 

 

2.1.2. Ladders and Platforms: 

 

If applicable the leaders and platforms should be inspected as per General  Requirements Para 1.6. 

 

2.1.3. Insulation Inspection: 

 

If vessel is insulated, the inspection of the insulation should be performed as per  General requirements Para 1.2.1. In case CUI is suspected than remove the insulation  from the affected area and inspect the shell as per General Requirements 1.2.2.  

 

2.1.4. Shell and Heads:  

 

If vessel is not insulated than inspection of heads and shell should be performed as  per General Requirements 1.2.2. 

  2.1.5. Welds:  

 

The structural, nozzle and attachment welds should be performed as per General  Requirements Para 1.3. 

Inspection Manual/Section‐5/Specific Requirements‐2 (Drums & Vessels)   Page 2‐2 

 

2.1.6. Nozzles:  

 

All of the nozzles should be inspected as per General Requirements Para 1.5. 

 

2.1.7. Attachments:  

 

Inspection of all of the attachments should be performed as per General  Requirements Para 1.8 

 

2.1.8. Gauges:  

 

Inspect condition of all of the gauges as per General Requirements Para 1.7   

2.1.9. Grounding Connection:  

 

Integrity of the grounding connection should be checked as per General Requirements  Para 1.9. 

 

2.1.10. Gaskets:  

 

Check for the leaks and gasket integrity as per General Requirements Para 1.10   

2.1.11. Attached Piping:  

 

a. Inspect the general condition of the attached piping. To determine if the  attached piping is not exerting undue stress on the vessel, attention should  be paid to the pipe supports on the piping directly attached to the vessel. 

The unsupported piping exerts the stress on the localized areas of the vessel  which could be above the designed limits of the vessel. The pipe support  inspection should be extended to at least to the 1st support away from the  vessel.  

 

b. Look for the vibrating sections of piping directly attached to the vessel. 

Vibration trend of the piping can be determined by shaking the piping with  light force. The vibrating section of attached piping can induce the 

mechanical fatigue at the nozzle weld areas.  

 

2.2.  Internal Inspection:  

 

Vessel should be prepared for internal inspection as mandated in section 4. 

 

2.2.1. Shell & Heads:  

 

a. The shell, heads, drain & gas boots (if applicable) should be inspected as per  General Requirements Para 1.2.2. 

 

Inspection Manual/Section‐5/Specific Requirements‐2 (Drums & Vessels)   Page 2‐3 

b.  The area of the shell or head below and above the normal product level is  typically susceptible to pitting and general corrosion. Sometimes the 

generalized wall loss takes place which is not easy to detect visually. The Zero  degree  Ultrasonic thickness measurement should be done in this case.   

 

c. The area of the shell adjacent to the baffle plate (on the downstream side for  separators) is susceptible to erosion, pitting and general corrosion. This area  should also be examined with ultrasonic to determine the actual wall thickness  of the shell.  

 

d. Depending upon the contents of the vessel, the bottom of the vessels  especially areas around the drain nozzles and the drain boot are susceptible  to under deposit and various kind of the corrosion mechanisms including  sour (wet H2S damage) and biological corrosion pitting.  

 

e. If the wall loss falls below the design tmin, the fitness for service analysis  should be conducted using the guide lines of API‐510 Para, 7.4. If the  analysis determines that the corroded area is not fit for continuous service  at the design parameters, the damaged area should be restored using  approved welding procedures.  

 

f. If restoration of excessively corroded areas is not possible at time being the  vessel should be derated and operated at reduced pressure limits until the  repair is done. New working pressure should be calculated as follows. 

 

• New working pressure due to corrosion wall loss on shell:  

 

0.6    

• New working pressure due to corrosion wall loss on dished head:  

 

0.1    

Whereas   t = Measured minimum thickness in corroded areas (in inches)  P = De‐rated working pressure (measured in psi) 

E = Joint efficiency ( E=1 if the corroded areas is away from  weld) 

    R = Radius in vessel ( in inches) 

      S = The allowable stress, (1/4 times tensile strength for vessels   Manufactured before 1999, and 1/3.5 times tensile strength  for vessels manufactured after 1999). 

 

g. The PSV setting on the derated vessel should be adjusted accordingly.  

 

h. Since the corrosion process is active in the derated vessels, further  deterioration is eminent during the derated service,  (unless some 

Inspection Manual/Section‐5/Specific Requirements‐2 (Drums & Vessels)   Page 2‐4 

operational procedures are not altered relative to the active demerge  mechanisms). Hence an ultimate safe thickness value (ultimate required  tmin) of the corroded shell should be fixed. The vessel must come out of  service if the minimum thickness of the subject corroded area falls below  this ultimate required tmin.  Due to this reason the subject corroded areas  must be periodically monitored with ultrasonic scanning (from outside). The  time period of monitoring should be determined based on the corrosion  rate, and the severity of the service. 

 

i. Once the ultimate required tmin is determined the remaining life of the  vessel (in derated service) should be determined as given below.  The  remaining life will determine the time interval allowed for the continued  service. 

 

.  

        

   

   

      

 

tprev =   The min thickness at time of previous inspection. (if no  thickness is available the design thickness should be used.  

tlatest =  The measured minimum thickness at present. 

tmin req =  The ultimate minimum thickness decided.  

 

Supplementary note:  

 

i. This approach should also be used to determine the remaining life  for vessels which are not in the derated service. 

 

ii. If enough OSI data for the corroded area is available so that the long  term and short term corrosion rates can be calculated (as given is  API‐510 Para 7.1.1.1). The highest of two should be used to  determine the remaining life. However it must be noted that the  general corrosion rate of the vessel might not be applicable at the  localized area which shows excessive  corrosion. Therefore it is safe  to develop separate corrosion rate of these areas with stringent  approach. 

  

2.2.2. Coated Vessels: 

 

If vessel is internally coated the inspection should be done according to General  requirements Para 1.2.3. 

 

2.2.3. Lined Vessels: 

 

Inspection Manual/Section‐5/Specific Requirements‐2 (Drums & Vessels)   Page 2‐5 

The vessels in erosive services are internally lined with the metallic liners or weld 

overlaid.  Following are the minimum requirements for the proper inspection of the weld  lining inspection.   

 

a. No corrosion is occurring either on the surface of the lining or below.  

 

b. The lining is properly installed, and no imperfections like disbanded or cracking  exist. All weld overlaying should be inspected with Liquid Penetrant inspection. 

 

c. Bulges or buckling of internal liners usually indicates that the process fluid or  gas has been trapped beneath the liner. This may present a potentially  dangerous situation if the pressure has not been relieved prior to inspection. 

Such situation should be carefully reviewed prior to initiating any inspection  work   inside of the pressure vessel. The trapped fluid could be an explosive  mixture of hydrocarbons. All means should be adopted to relieve the trapped  pressure behind the bulges.  

 

d. In case of the bonded lining (done by the explosion lining process), where ever  suspected the integrity of the lining should be checked with ultrasonic. 

  

e. Check shell and nozzle thicknesses just above and below cladding. 

Sometimes the shell besides the lining shows excessive generalized  corrosion which could not be judged by visual inspection.  

 

2.2.4. Weld Inspection: 

 

Inspect all internal structural, nozzle and attachment welds as per General 

Requirements Para 1.3. The attachment welds are of significant importance. Most of  the vessel failures are associated with the defects originating from the attachment  welds. If the service related defects are suspected at some welds, the Magnetic  particle inspection (if not already part of scope) should be added to the scope of  inspection.  

 

2.2.5. Nozzles Inspection: 

 

a. All  nozzles (including manways) should be checked thoroughly, for  corrosion or any other service related defects.  

 

b. Check nozzles for plugging with deposits, especially small draw‐off and  instrument nozzles.  

 

c. Look at the gasket face for corrosion and erosion. The gasket faces are  prone to have crevice corrosion if the debris is trapped in between.  

 

d. Report any condition that could affect the sealing and cause the leaks. Over  torque can sometimes damage the mating faces of the flanges.   

 

Inspection Manual/Section‐5/Specific Requirements‐2 (Drums & Vessels)   Page 2‐6 

e. Look for the appropriate depth of machined serrations, both on the nozzle  flanges nozzle and the cover (or mating flange) gasket faces. Best visual  judgment is adequate to find out if the serration depth is appropriate or  not, however the micrometer measurements can also be taken if required.   

 

2.2.6. Internal Attachments: 

 

a. Check the structural integrity of the internal attachments like vortex breaks,  Baffle plates, inlet deflectors, impingement plates, stiffener rings, demister  pad holding assemblies etc. The damage to these attachments significantly  affects the operation parameters of the vessel and alters the damage  mechanism. Repairs should be recommended if the attachments are found  excessively corroded, dismantled or damaged to the extent that intended  function is not achievable. 

 

b. If applicable the demister pads and/or filters should be removed and  cleaned for inspection. Replace these components if found corroded or  damaged to the extent that the mesh or assembly would not survive the  next service cycle.  

 

c. Check inlet distributors and surrounding area for abnormal wear or  corrosion 

  

2.2.7. Magnetic particle inspection should be added to the scope of inspection, if the  cracking is suspected. The scope and extent of MT is decided based upon the vessel  history, potential damage mechanism and the severity of the service conditions. 

However Wet Fluorescent MPI or LPI (whichever applicable) must be done  at the  welds in following vessels.  

 

a. Vessels in sour service.  

 

b. Vessels in refrigerated service. 

 

c. Vessels in hydrogen service. 

 

d. Vessels subjected to thermal and mechanical fatigue. 

 

e. Where ever stress corrosion cracking of any kind is suspected. 

   

2.2.8. Internal instruments like floaters, thermo wells, Corrosion coupons, internal cathodic  protection anodes etc (if not disassembled) should be inspected for the integrity and  the intended functions. These instruments could be subjected to the resonant  vibration because of the flow dynamics inside the vessel. Check for the fatigue signs  on these instruments.   

 

2.3. Additional Inspection with the specialized None destructive methods like AUT, acoustic  emission, remote visual, magnetic flux leakage and Eddy currents etc. should be carried out as 

Inspection Manual/Section‐5/Specific Requirements‐2 (Drums & Vessels)   Page 2‐7 

the special requirements. The detailed procedure and precautions for using these techniques  is beyond the scope of this manual.  

 

In document SANTO DOMINGO IS BURNING Johan Mijail (página 32-48)

Documento similar