• No se han encontrado resultados

CAPITULO I Análisis del sector de las frutas y hortalizas

I. 3.3.- Características comerciales y de mercado

6421 6422

7.1 INTRODUCTION

6423 6424

A new alternative methodology will be proposed for preparing regulated 6425

ensuring product quality or patient safety. This Baseline Guide follows 6432

the principles of ASTM Standard E2500-2007.

6433 6434

Although the premise of this HVAC guide is to provide the "how" of 6435

implementing those HVAC requirements and concepts found in the baseline 6436

there is always room for improvement, but the interpretations provided 6446

Key concepts and terminology proposed for the Installation and 6450

Verification Guide are used extensively in this guide. The Baseline 6451

Guide will provide more depth regarding these concepts and terms.

6452 6453

7.2 PHILOSOPHY

6454 6455

The commissioning and qualification philosophy used to date 6456

incorporates Good Engineering Practices (GEP) and Impact Assessment.

6457

Systems and components that were designated as Direct Impact were 6458

subject to qualification, in addition to commissioning. The difficulty 6459

encountered in this process is that some companies found it difficult 6460

to leverage commissioning activities and documentation into 6461

qualification, so they re-commissioned a system to gather qualification 6462

documents. Some of the compliance-related activities included general 6463

engineering-focused activities that added little or no compliance value 6464

(such as qualifying fan speeds or prefilters).

6465 6466

The new methodology is based on:

6467

 Use of risk assessments (instead of impact assessments) to determine 6471

the scope and extent of required verification in the overall Risk 6472

Management Process, which is related to patient safety 6473

 Notion of Design Space 6474

 Focusing on practices that lead to achieving fitness for purpose.

6475 6476

7.3 PRINCIPLES

6477 6478

Key principles that provide the basis for developing engineering 6479

requirements are:

6480 6481

 The assessment and designation of criticality should be primarily 6482

based on impact on the safety and efficacy of the drug product to 6483

the patient 6484

6485

 Critical Quality Attributes (CQAs) should drive the focus of the 6486

risk assessment along with Critical Process Parameters (CPPs) 6487

6488

 Risk assessment shall be performed in the "design space", the 6489

intersection of CQAs and CPPs, and is subject to regulatory 6490

assessment and approval.

6491 6492

 The Installation and Verification process shall have value added 6493

activities and shall remove those activities that are wasteful and 6494

non-value adding.

6495 6496

 Verification practices performed solely for regulatory compliance 6497

should be avoided. 2 6498

6499

7.3.1 Good Engineering Practice 6500

6501

Good Engineering Practice (GEP) is the practice under which all 6502

engineering activities and documentation are created. It applies to all 6503

facilities, not just pharmaceutical facilities. GEP encompasses the 6504

following:

6505 6506

 Design and installation that takes full account of cGMP, safety, 6507

health, environmental, ergonomic, operational, maintenance, 6508

recognized industry guidance, and statutory requirements.

6509 6510

 Professional and competent project management, engineering design, 6511

procurement, construction, installation and commissioning 6512

demonstrating functionality per design specifications.

6513 6514

 Appropriate documentation, including design concepts, design 6515

schematic drawings, as-installed drawings, test records, maintenance 6516

and operations manuals, statutory inspection certificates, etc.

6517 6518

Well planned commissioning activities and documentation following sound 6519

Engineering Principles and Good Engineering Practices make a 6520

significant contribution in preparing for and achieving first time 6521

success to meet installation and verification requirements.

6522 6523

2 If a practice adds to the assurance that the equipment or system will work as intended then that practice should be performed whether or not the system is part of GMP manufacturing operations. If it does not, then that practice should not be performed unless specifically required for compliance.

7.3.2 GMP 6524

6525

Sustainability and Commissioning/Verification 6526

6527

TEXT NEEDED 6528

6529

7.4 REGULATORY EXPECTATIONS

6530 6531

TEXT NEEDED 6532

6533

US – This approach is recognized by the FDA as ONE method of verifying 6534

fitness of the HVAC system for production. Activities in this approach 6535

follow the principles in ASTM E2500.

6536 6537

EU – unknown at this time whether EU regulators will accept less 6538

voluminous Qualification packages.

6539 6540

Other - ? 6541

6542

Regulatory expectations are covered by the appropriate ISPE Facility 6543

Baseline Guide. As these expectations sometimes change, this guide 6544

defers to the Baseline Guides.

6545 6546

7.5 KEY CONCEPTS OF VERIFICATION

6547 6548

The verification process for HVAC Systems is a subset of the 6549

verification process for the manufacturing system. These key concepts 6550

have been driven by the FDA Initiative Pharmaceutical cGMP‘s for the 6551

21s Century – A Risk Based Approach, and by ICH Q9 Quality Risk 6552

Management. The overall direction is a shift toward the safety of the 6553

07 to the installation and verification of HVAC Systems.

6557 6558

The goal of this approach is to improve patient safety while 6559

controlling costs and reducing non-value adding effort.

6560 6561

It should be noted that these Key Concepts focus on patient safety and 6562

product quality (GMP). The verification of the specification and 6563

design as it impact worker safety, health, environmental and other non-6564

GMP concerns should also be considered.

6565 6566

7.5.1 Risk-based and Science-based Approach 6567

6568

The level of risk to product quality should be based on scientific 6569

knowledge that leads to protection of the patient. The level of effort 6570

risk-based decision to insure that manufacturing systems are designed 6574

and verified to be fit for their intended use.

6575 6576

Considerations include Critical Quality Attributes (CQAs), Critical 6577

Process Parameters (CPPs), process control strategy and prior 6578

production experience.

7.5.2 Critical Aspects of Manufacturing Systems 6585

6586

Critical Aspects of Manufacturing Systems are typically functions, 6587

features, abilities, and performance characteristics necessary for the 6588

manufacturing process and systems to ensure consistent product quality 6589

and patient safety.‖ HVAC systems may affect the manufacturing system 6590

and the critical aspects. Verification activities should focus on the 6591

critical aspects of the Manufacturing system and HVAC subsystem‘s 6592

effect.

6593 6594

7.5.3 Quality by Design 6595

only phase activity.

6599 6600

7.5.4 Good Engineering Practice 6601

6602

Good Engineering Practice a set of established engineering methods and 6603

standards that are applied throughout the life cycle to deliver 6604

appropriate and effective solutions. For HVAC systems GMP 6605

requirements, code requirements including sustainability requirements 6606

and energy efficiency, safety, health environmental, ergonomic 6607

operational, and maintenance must be address. Preceding chapters 6608

discuss how to implement Good Engineering Practice for HVAC systems.

6609 6610

7.5.5 Subject Matter Experts 6611

6612

Subject Matter Experts have specific expertise and responsibility in a 6613

particular area or field . For HVAC Systems this could include the 6614

HVAC Engineer, quality unit, automation, or operations.

6615 6616

7.5.6 Use of Vendor Documentation 6617

equipment or system.

6623 6624

7.5.7 Continuous Improvement 6625

6626

Continuous improvement can happen as information is gained from 6627

operations. Improvements can be based on periodic reviews and 6628

evaluation, operational data and root-cause analysis of failures. For 6629

HVAC systems energy optimization is typically reviewed. Such 6630

improvement should be encouraged, although current Change Management 6631

programs often discourage change for any reason.

6632 6633

7.6 DESIGN, SPECIFICATION, VERIFICATION, AND ACCEPTANCE

they relate to the overall specification, design and verification 6638

process for the manufacturing system as well as HVAC subsystem. For a 6639

7.6.1 Requirements Definition 6643

6644

Product Knowledge, Process Knowledge, Regulatory Requirements and 6645

Company Quality requirements all must be considered when determining 6646

the requirements for the manufacturing systems and HVAC system. The 6647

requirements definition is driven by patient safety. See chapter 3 for 6648

more detail.

6649 6650

7.6.2 Specification and Design 6651

7.6.3 Verification 6656

Commissioning Plan or Verification Plan for Facility and Utility 6661

Systems will include the HVAC system and controls.

6662 6663

The HVAC engineer's role in verification will be different from in the 6664

impact assessment process. Under the ISPE Commissioning &

6665

Qualification Baseline Guide, systems were determined to be either 6666

direct impact or indirect impact. The HVAC engineer was part of a team 6667

that supported, developed, and executed commissioning and qualification 6668

qualification for direct impact systems by leveraging documents and 6673

procedures to streamline the process and reduce redundant testing and 6674

non-value added activities.

6675

making such a change.

6681

not if this is a direct or indirect impact system, but rather what are 6686

the elements of this system that are critical to product quality and 6687

patient safety, and how can we manage those risks appropriately to 6688

maintain or improve our overall product quality?

6689 6690

The interdisciplinary expert team forms the foundation for developing a 6691

risk management plan. Team members decide on methodologies to 6692

determine acceptable levels of risk and appropriate tools to evaluate 6693

risk (e.g. FMEA) after identifying the User Requirements. User 6694

Requirements should identify the Critical Process Parameters (CPP), 6695

Critical Quality Attributes (CQA) and other critical aspects related to 6696

product quality and patient safety.

6697 6698

Once the critical aspects (CPP, CQA, etc.) have been identified by the 6699

interdisciplinary team and documented, the quality unit then approves 6700

this document as the basis for the Verification Plan that will be 6701

developed. Furthermore, engineers need to know what type of tests the 6702

quality unit will expect to be performed after the verification process 6703

is complete in order to prepare systems to pass these tests.

6704 6705

Verification, similar to ―commissioning and qualification (for direct 6706

impact systems)‖, is one process that covers the activities, testing, 6707

and documentation required to evaluate systems, equipment, and 6708

tests to be performed are developed by the Subject Matter Expert (SME).

6712

For example, the HVAC SME would design a verification plan that would 6713

verify the acceptance criteria that meets the critical aspects (CQA, 6714

CPP …) within the framework of the risk management plan.

6715 6716

For an overview of the verification process, refer to figure 7.1:

6717 6718

7.6.4 Commissioning & Qualification process – SEE APPENDIX 6719

6720

7.6.5 Acceptance and Release 6721

6722

The acceptance and release phase confirms that the manufacturing system 6723

and support HVAC system are fit for their intended use. This is the 6724

last check before initial operation.

6725 6726

7.7 SUPPORTING PROCESSES

6727 6728

The activities described here can be part of the Specification, Design 6729

and Verification (SDV) Process. They occur throughout the SDV process.

6730 6731

7.7.1 Quality Risk Management (QRM) 6732

process for the manufacturer. The Risk Assessment for the HVAC system 6736

should be addressed in the overall Risk Assessment activity..

6737 6738

7.7.2 Design Review 6739

6740

Design reviews are planned systematic reviews of specifications, 6741

design, design development and continuous improvement changes performed 6742

throughout the life cycle of the manufacturing system. For HVAC 6743

systems in the design phase, reviews typically occur at the basis of 6744

design (BOD), schematic design, design development and construction 6745

document phases. HVAC equipment specifications are often not available 6746

until the construction document phase and their review is critical to 6747

system quality.

6748 6749

7.7.3 Change Management 6750

6751

Change Management should be implemented on changes that affect critical 6752

aspects of the manufacturing system, both before and after acceptance.

6753

After acceptance, changes that affect GMP critical parameters need to 6754

be approved by the Quality unit prior to implementation. With 6755

continuous improvement as a goal of the FDA initiative, it is expected 6756

that systems that have been verified and accepted for intended use will 6757

be modified to achieve improved patient safety or reduce operating 6758

costs as opportunities arise during the manufacturing system‘s life 6759

cycle.

6760 6761 6762