• No se han encontrado resultados

MEXICO INDEPENDIENTE

1.6 LA GLOBALIZACIÓN

Commissioning engineers can configure site commissioning data by using a hand-held tool on site when the following conditions are met:

l Commissioning engineers are capable of configuring radio link data on the OptiX RTN 620.

l Commissioning engineers are aware of the radio link data planning for the site.

l Commissioning engineers carry hand-held tools.

Table 3-2 Configuring site commissioning data by using a hand-held tool

Commissioning Item Remarks

Powering On the Equipment Required

Configuring Site Commissioning Data by Using a Hand-Held Tool

Connecting a Hand-held Tool to the IDU

Required

Configuring NE Attributes Required Configuring a Radio Link Required

Checking Alarms Required

Testing Connectivity of the Cables

Testing Connectivity of E1 Cables with a Hand-Held Tool

Required when E1 cables are used on the site

Testing Connectivity of the Ethernet Cables

Required when Ethernet cables are used on the site Testing Connectivity of

Fiber Jumpers

Required when optical fibers are used on the site

Aligning Antennasa Aligning Single-Polarized Antennas

Required when radio signals are transmitted by single-polarized antennas Aligning Dual-Polarized

Antennas

Required when radio signals are transmitted by dual-polarized antennas

NOTE

a: Before aligning antennas, you must power on the equipment and configure site commissioning data on both ends of the radio link.

3.1.2 System Commissioning Items

System commissioning involves the commissioning of the entire radio transmission network.

The purpose of system commissioning is to ensure that various services are transmitted normally and protection functions are implemented on the radio transmission network.

Table 3-3 System commissioning items

Commissioning Item Remarks

Configuring the Network-Wide Service Data

Required

Testing the E1 Service

Testing the E1 Services by Using a BER Tester

Required when the E1 service is available and a BER tester is available on site

Testing the E1 Service Through PRBS

Required when the E1 service is available and a BER tester is unavailable on site

Testing Ethernet Services

Testing Ethernet Services by Using the LB Function

Required when the NEs at both ends support the ETH-OAM function

Testing Ethernet Services by Using the Ping Function

Required when the NE at one end supports the ETH-OAM function

Testing Ethernet Services by Using Laptops

Required when neither NEs at both ends supports the ETH-OAM function

Testing AM Switching

Testing AM Switching by Using a BER Tester

Required when the AM function is enabled and a BER tester is available on site

Testing the AM Switching Without a BER Tester

Required when the AM function is enabled and no BER tester is available on site

Testing Protection Switching

Testing IF 1+1 Switching

Required when radio links are configured in 1+1 HSB/FD/SD mode

Testing N+1 Protection Switching

Required when N+1 protection is configured

Testing SNCP Switching

Required when the SNCP service is configured

Testing ERPS Required when ERPS is configured Testing the

Two-Fiber Bidirectional MSP Switching

Required when two-fiber bidirectional MSP is configured

Testing Linear MSP Switching

Required when 1+1/1:N linear MSP is configured

Querying Clock Status Required

Testing the 24-Hour BER Required when the E1 service is available

3.2 Documents and Tools Preparation

Based on the scale of the radio transmission network, commissioning engineers can adopt the hop commissioning method or network commissioning method.

Documents

Before commissioning the equipment, you must make the following documents available:

l Engineering and design documents, including:

Network Planning

Engineering Design

l Commissioning guide documents, including:

OptiX RTN 620 Radio Transmission System Commissioning Guide

OptiX RTN 620 Radio Transmission System Configuration Guide

Tools

Table 3-4 lists the tools required for the commissioning task.

Table 3-4 List of tools and meters

Tool and Meter Application Scenario

Adjustable wrench, screwdriver, telescope, intercom, socket-head wrench, multimeter and a test cable with a BNC connector at one end, north-stabilized indicator

Aligning the antennas

Laptop on which the LCT is installed l Configuring site commissioning data

l Testing connectivity of E1 cables

l Querying the DCN status

Hand-Held Tool Configuring site commissioning data

BER tester l Testing connectivity of E1 cables

l Testing E1 services by using a BER tester

l Testing the AM switching by using a BER tester

l Testing IF 1+1 switching

l Testing N+1 protection switching

l Testing SNCP switching

l Testing two-fiber bidirectional MSP switching

l Testing linear MSP switching

l Testing 24-Hour BER

Tool and Meter Application Scenario

Network tester Testing connectivity of Ethernet cables

Optical power meter, short fiber jumper Testing connectivity of fiber jumpers NMS server on which the Web LCT is

installed

Network commissioning by using the Web LCT

E1 jumper Testing the 24-hour BER

3.3 Checking Commissioning Conditions

Before performing site commissioning and system commissioning, check whether the equipment meets the commissioning requirements.

3.3.1 Checking Site Commissioning Conditions

Before performing site commissioning, you need to check the equipment and the weather.

3.3.2 Checking System Commissioning Conditions

Before performing system commissioning, you need to check the equipment and the weather.

3.3.1 Checking Site Commissioning Conditions

Before performing site commissioning, you need to check the equipment and the weather.

The site commissioning conditions are listed as follows:

l The hardware installation must be complete and pass the installation check.

l The power for the equipment must be available.

l The service signal cables that are connected to other equipment must be routed as required.

l The site conditions and antenna commissioning personnel must meet the requirements for operations at heights.

l The weather must be favorable without rain, snow, or mist.

3.3.2 Checking System Commissioning Conditions

Before performing system commissioning, you need to check the equipment and the weather.

The system commissioning conditions are listed as follows:

l The NE commissioning of the radio equipment at both ends of the radio link must be complete.

l The weather must be favorable for outdoor work. There should be no rain, snow or fog between two sites.

4 Site Commissioning Guide

About This Chapter

This topic describes how to perform all site commissioning items.

4.1 Powering On the Equipment

By checking the process of powering on equipment, you can check whether the hardware system of the equipment and the power system are working properly.

4.2 Configuring Site Commissioning Data by Using the Web LCT

This topic describes how to configure site commissioning data by using the Web LCT.

4.3 Configuring Site Commissioning Data with a Hand-Held Tool

This topic describes how to configure site commissioning data by using a hand-held tool.

4.4 Testing Connectivity of Cables

In the installation process, the hardware part of service cables may become faulty or the service cables may be incorrectly connected. To ensure that services run normally, you need to test connectivity of the cables.

4.5 Aligning Antennas

Aligning antennas is the most important activity in site commissioning, and its result has a direct impact on the performance of radio links.

4.6 Querying the Status of Radio Links

After aligning the antennas, you need to query the status of radio links and ensure that the radio links are in normal status.

4.7 Querying DCN Status

The NMS manages NEs through DCN channels. Querying the radio links through the HOP management function on the Web LCT, you can check whether the DCN of radio links runs normally.

4.1 Powering On the Equipment

By checking the process of powering on equipment, you can check whether the hardware system of the equipment and the power system are working properly.

Prerequisite

l The hardware installation must be complete and pass the installation check.

l The power supply must be available and the fuse capacity must meet the requirement of the equipment.

l The power supply (such as the power box of the cabinet) must be turned off.