• No se han encontrado resultados

GLAPION, Jmn

In document Los consejeros de Carlos V (página 166-169)

The project’s potential environmental impacts and their significance have been assessed using the methodology described in Section 8.2 above. A summary of these impacts and their significance is presented in Table 8.4.

WAPDA

Table 8.4: Significance of Environmental Impacts

Impacts Phase Receptor

Mitigation and Enhancement Measure Residual Significance

Land Acquisition and Land Use Change; preparation of construction facilities

Pre-construction Low Minor Low Adverse Construction camps and other construction facilities to be established on WAPDA owned land.

Re-plantation plan to be prepared and implemented.

Negligible

Contractor mobilization Pre-construction Medium Moderate Moderate Adverse Contractor to prepare and implement a traffic management plan. Temporary by-pass routes.

Community awareness.

Low Adverse

Topography:

blasting and cutting for powerhouse;

blasting and cutting at borrow sites;

Medium Major Moderate Adverse no excessive excavation; and

use of alternative excavation methods wherever possible.

Negligible

Geology and Seismology:

risk of seismic activity.

All Phases High Major Major Adverse foundation design of the powerhouse to consider probability of earthquake at the earliest design stage;

Method Statements and Risk Assessments with particular attention to blasting material and blasting techniques; and closure of existing Tunnel 4 to join with the new tunnel and for constructing the raised intake will result in the interruption of irrigation releases through tunnel 4; and

operation – the Tunnel 4 capacity will be reduced by

Construction: Medium Moderate Moderate Adverse connection tunnels will be carried out during the annual canal closure and periods of low demand; and

Releases from tunnels 1-3 and 5 will be adjusted to meet the irrigation water demands and power generation.

the reservoir will continue to be operated to ensure meeting the irrigation water demand.

Negligible

Impacts Phase Receptor

Mitigation and Enhancement Measure Residual Significance around 5%.

Operation: High Moderate Major Adverse Negligible

Surface Water Quality:

many sources of discharge and effluents.

Surface Water Monitoring Program;

Select access roads to avoid run off to river;

pre-treated sewage prior to discharge;

Wastewater Treatment Plan;

Oil and Chemical Spill Response Plan;

Waste Management Plans;

Store and handle all hazardous substances in accordance with their MSDS;

Install oil and water separators and settling ponds; and

Upon completion of decommissioning, disturbed areas will be contoured and revegetated to minimize the potential for soil erosion and water quality related impacts.

Low adverse

Negligible

Ground Water Quality:

piling for foundations;

accidental spills and leakage;

and

Ground Water Monitoring Program;

work within the requirements of the management plans contained within the EMMP;

staff training;

all sanitary effluent will be treated prior to discharge;

treatment plant will conform to international standards;

drainage system will be designed so that all spills will be drained and collected in a sump for further appropriate disposal; and

Oil and chemical storage and vehicle wash and oil change facilities will be on an impermeable surface to avoid percolation.

Negligible

Wastes:

large volume of spoil;

possible risk of erosion into the Indus River;

Construction and

De-commissioning:

Medium Moderate Moderate Adverse reduce volume of material requiring disposal;

re-use where possible;

disposal of spoil at designated depressed area;

only remove equipment and machinery leaving

Negligible

WAPDA

Mitigation and Enhancement Measure Residual Significance

leakage, spillage from other wastes (domestic and hazardous); and

camp wastes

disposal of demolition material.

Operation:

Low Minor Negligible

infrastructure in place for re-use for other purposes;

Waste Management Plans; and

Excavated Material Disposal Plan.

Demolition material disposal plan

Landslides:

Risk of landslide resulting from excavation and blasting

extraction from top down;

use of pre-designed support systems;

use cushion blasting in confined areas;

Method Statements and Risk Assessments with particular attention to blasting material and blasting techniques; and

include in Emergency Preparedness Plan.

Low Adverse

fish mortality from river turbidity

surface disturbance from

storage and use of hazardous materials;

re-vegetation, especially of slopes, of fast-growing indigenous species;

road edge buffer replanting;

Tree Plantation Plan; and

decommissioning would be followed by contouring and re-vegetation.

Medium Moderate Moderate Adverse covering standing material and transported material to prevent dust blows;

washing of construction vehicles;

specific and agreed routes for traffic;

speed limits; and

Medium Major Moderate Adverse Ambient noise:

restricting / limiting timing of blasting activity;

fitting applicable construction machinery with mufflers;

Low Adverse

Impacts Phase Receptor

Mitigation and Enhancement Measure Residual Significance

blasting

power plant operation

Operation

Low Minor Negligible

maintaining and powering down all plant items when not in use;

avoid unnecessary revving of vehicle engines;

use quietest work methods and plant items where practicable;

provision of noise barriers at excessive noise producing areas (such as blasting sites); and

informing the communities of activities taking place such as blasting.

provision of PPE i.e. ear muffs and plugs;

provision of vibration absorbing gloves;

instruction in the proper use of equipment;

frequent breaks;. 10 minutes per hour; and

manage and properly design all blasting activities.

Landscape and Visual Intrusion:

new planting and landscape restoration.

Landscape Plan. Positive

Beneficial

transport of construction labor;

Construction and

De-commissioning

Medium Moderate Moderate Adverse Traffic Management Plan

Provision of by pass routes

Minimizing the duration of right bank road closure

Negligible/low adverse

WAPDA

Mitigation and Enhancement Measure Residual Significance

closure of right bank road

additional traffic to remove demolished material; and

transport of decommissioning labor.

Increased activities affecting Fauna / Wildlife / Vegetation:

disruption to areas that are currently used by wild fauna including birds/migratory birds.

Construction Medium Moderate Moderate Adverse avoid positioning spoil in areas used by fauna;

provide corridors for animal movement;

relocation of species; and

no illegal hunting or poaching.

Negligible

Flora / Vegetation:

loss of vegetation leads to soil erosion.

Construction and

De-commissioning

Medium Major Major Adverse avoid dumping material in vegetated areas;

re-provide plantations in open spaces and practice watershed management;

enhance flora environment by planting fruit trees and ornamental shrubs;

use fast-growing species; and

use grasses to assist slope and soil stability

Positive

Potentially All Medium Moderate Moderate Adverse during Monsoon runoff will be diverted to adjacent

depressions and from there to river after settling. Negligible

Bird collision with transmission

cables Construction and

Operation

Medium Moderate Moderate Adverse attaching markers/balls with the cables Negligible

8.4 Impacts during Pre-construction Stage

In document Los consejeros de Carlos V (página 166-169)